Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, Kingsville |
---|---|
Assessment Year | 1997 |
Principal Product | Metal valve parts and custom made metal parts |
NAICS | n/a |
SIC | 3599 - Industrial Machinery, Nec |
Sales | $1,000,000-$5,000,000 |
# of Employees | 65 |
Plant Area (Sq.Ft.) | 38,500 |
Annual Production | 9,000 Pieces |
Production Hrs. Annual | 6,448 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $25,632 | 620,457 | kWh | $0.04 |
Electricity Demand | $17,792 | 2,224 | kW-months/year | $8.00 |
Electricity Fees | $938 | - | $ | - |
TOTAL ENERGY COSTS | $65,255 | |||
RECOMMENDED SAVINGS* | $52,966 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Primary Product | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $4,621 Cost: $12,410 |
$3,720 | 89,097 | $901 | 113 | - | - | - | - |
$3,720 89,097 kWh |
$901 113 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,696 Cost: $6,689 |
$1,216 | 29,015 | $480 | 60 | - | - | - | - |
$1,216 29,015 kWh |
$480 60 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $892 Cost: $450 |
$892 | 21,395 | - | - | - | - | - | - |
$892 21,395 kWh |
- - kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $4,800 Cost: $243 |
- | - | - | - | $4,800 | 872,720 | - | - |
- - kWh |
- - kW-months/year |
$4,800 872,720 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $3,231 Cost: - |
- | - | - | - | $3,231 | 7,800 | - | - |
- - kWh |
- - kW-months/year |
$3,231 7,800 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $312 Cost: - |
- | - | - | - | $312 | 156 | - | - |
- - kWh |
- - kW-months/year |
$312 156 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $37,414 Cost: $14,190 |
- | - | - | - | - | - | $37,414 | - |
- - kWh |
- - kW-months/year |
- - lb |
$37,414 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $52,966 Cost: $33,982 |
$5,828 | 139,507 | $1,381 | 173 | $8,343 | 880,676 | $37,414 | - | $5,828 139,507 kWh |
$1,381 173 kW-months/year |
$8,343 880,676 lb |
$37,414 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Primary Product | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Primary Product |