IAC Assessment: KS2316
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: KS2316
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Kennesaw State
Assessment Year 2023
Principal Product Polymers and Powder Resins
NAICS 325211 - Plastics Material and Resin Manufacturing
SIC 2821 - Plastics Materials And Resins
Sales $100,000,000-$500,000,000
# of Employees 49
Plant Area (Sq.Ft.) 160,000
Annual Production 60,000,000 Pounds
Production Hrs. Annual 8,400
Location (State) GA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $934,767 10,800,684 kWh $0.09
Natural Gas $685,391 197,320 MMBtu $3.47
TOTAL ENERGY COSTS $1,644,828
RECOMMENDED SAVINGS* $291,517 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS Savings:
$11,534
Cost:
$2,766
- - $11,534 3,324 - - -
-
kWh
$11,534
3,324
MMBtu
-
-
$
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$1,197
Cost:
$1,784
- - $1,197 345 - - -
-
kWh
$1,197
345
MMBtu
-
-
$
03: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES Savings:
$1,228
Cost:
$2,463
- - $1,228 354 - - -
-
kWh
$1,228
354
MMBtu
-
-
$
04: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$3,417
Cost:
-
- - $4,167 1,201 $(-750) - -
-
kWh
$4,167
1,201
MMBtu
$(-750)
-
$
05: 2.3417 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT Savings:
$125,127
Cost:
$627,000
$146,160 1,680,000 $(-14,633) (-4,217) $(-6,400) - $146,160
1,680,000
kWh
$(-14,633)
(-4,217)
MMBtu
$(-6,400)
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$9,198
Cost:
$29,442
$6,051 69,552 - - $3,147 - $6,051
69,552
kWh
-
-
MMBtu
$3,147
-
$
07: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$7,751
Cost:
$6,350
$6,468 74,340 - - $1,283 - $6,468
74,340
kWh
-
-
MMBtu
$1,283
-
$
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$12,336
Cost:
$29,920
$12,336 141,788 - - - - $12,336
141,788
kWh
-
-
MMBtu
-
-
$
09: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$49,691
Cost:
$246,356
$49,691 571,158 - - - - $49,691
571,158
kWh
-
-
MMBtu
-
-
$
10: 2.2622 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL Savings:
$17,892
Cost:
$156,412
$17,892 205,651 - - - - $17,892
205,651
kWh
-
-
MMBtu
-
-
$
11: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$52,146
Cost:
$422,182
$52,146 599,374 - - - - $52,146
599,374
kWh
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$291,517
Cost:
$1,524,675
$290,744 3,341,863 $3,493 1,007 $(-2,720) - $290,744
3,341,863
kWh
$3,493
1,007
MMBtu
$(-2,720)
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
MMBtu
-
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes