IAC Assessment: KU0119
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: KU0119
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Univ. of Kansas
Assessment Year 1984
Principal Product WHOLE HOG SAUSAGE
NAICS n/a
SIC 2011 - Meat Packing Plants
Sales $10,000,000-$50,000,000
# of Employees 100
Plant Area (Sq.Ft.) 0
Annual Production 24,000,000 Pounds
Production Hrs. Annual 2,646
Location (State) KS
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $123,157 2,757,620 kWh $0.04
Natural Gas $98,647 20,918 MMBtu $4.72
TOTAL ENERGY COSTS $221,804
RECOMMENDED SAVINGS* $49,804 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $30,608
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$21,545
Cost:
$16,000
- - $21,545 4,565 -
-
kWh
$21,545
4,565
MMBtu
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$6,576
Cost:
$5,000
- - $6,576 1,393 -
-
kWh
$6,576
1,393
MMBtu
03: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE Savings:
$4,583
Cost:
$7,400
$3,521 78,839 $1,062 225 $3,521
78,839
kWh
$1,062
225
MMBtu
04: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$4,150
Cost:
$3,590
- - $4,150 879 -
-
kWh
$4,150
879
MMBtu
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,365
Cost:
$3,208
$3,365 75,322 - - $3,365
75,322
kWh
-
-
MMBtu
06: 2.1222 INSTALL TURBULATORS Savings:
$2,558
Cost:
$1,261
- - $2,558 542 -
-
kWh
$2,558
542
MMBtu
07: 2.1212 OPERATE BOILERS ON HIGH FIRE SETTING Savings:
$2,034
Cost:
$50
- - $2,034 431 -
-
kWh
$2,034
431
MMBtu
08: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED Savings:
$1,240
Cost:
-
- - $1,240 263 -
-
kWh
$1,240
263
MMBtu
09: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES Savings:
$982
Cost:
$200
- - $982 208 -
-
kWh
$982
208
MMBtu
10: 2.2163 USE MINIMUM STEAM OPERATING PRESSURE Savings:
$939
Cost:
-
- - $939 199 -
-
kWh
$939
199
MMBtu
11: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$486
Cost:
$465
- - $486 103 -
-
kWh
$486
103
MMBtu
12: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$393
Cost:
$50
$393 8,792 - - $393
8,792
kWh
-
-
MMBtu
13: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$288
Cost:
$120
- - $288 61 -
-
kWh
$288
61
MMBtu
14: 2.2511 INSULATE BARE EQUIPMENT Savings:
$264
Cost:
$150
- - $264 56 -
-
kWh
$264
56
MMBtu
15: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$262
Cost:
$30
$262 5,862 - - $262
5,862
kWh
-
-
MMBtu
16: 2.2511 INSULATE BARE EQUIPMENT Savings:
$139
Cost:
$135
- - $139 29 -
-
kWh
$139
29
MMBtu
TOTAL RECOMMENDED Savings:
$49,804
Cost:
$37,659
$7,541 168,815 $42,263 8,954 $7,541
168,815
kWh
$42,263
8,954
MMBtu
TOTAL IMPLEMENTED Savings:
$30,608
Cost:
$20,040
$393 8,792 $30,215 6,402 $393
8,792
kWh
$30,215
6,402
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas