Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Univ. of Kansas |
---|---|
Assessment Year | 1984 |
Principal Product | BRASS PLUMBING SUPPLIES |
NAICS | n/a |
SIC | 3432 - Plumbing Fixture Fittings And Trim |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 4,000,000 Pounds |
Production Hrs. Annual | 4,550 |
Location (State) | KS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $244,765 | 3,791,911 | kWh | $0.06 |
Natural Gas | $74,843 | 15,472 | MMBtu | $4.84 |
TOTAL ENERGY COSTS | $319,608 | |||
RECOMMENDED SAVINGS* | $54,514 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $45,856 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $23,486 Cost: - |
$23,486 | 364,009 | - | - | - | - |
$23,486 364,009 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $12,840 Cost: - |
$12,840 | 199,004 | - | - | - | - |
$12,840 199,004 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4312 IMPROVE LUBRICATION PRACTICES |
Savings: $3,966 Cost: - |
$9,966 | 154,455 | - | - | $(-6,000) | - |
$9,966 154,455 kWh |
- - MMBtu |
$(-6,000) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $4,586 Cost: $3,000 |
$4,586 | - | - | - | - | - |
$4,586 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1122 RE-SIZE CHARGING OPENINGS OR ADD A MOVABLE DOOR ON EQUIPMENT |
Savings: $4,141 Cost: $2,000 |
$4,141 | 64,185 | - | - | - | - |
$4,141 64,185 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,229 Cost: $650 |
$1,229 | 19,050 | - | - | - | - |
$1,229 19,050 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $1,043 Cost: $1,200 |
$1,532 | 23,740 | $(-489) | (-101) | - | - |
$1,532 23,740 kWh |
$(-489) (-101) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $755 Cost: $500 |
- | - | $755 | 156 | - | - |
- - kWh |
$755 156 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $663 Cost: $1,200 |
- | - | $663 | 137 | - | - |
- - kWh |
$663 137 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7441 REPLACE BROKEN WINDOWS AND/OR WINDOW SASH |
Savings: $620 Cost: $920 |
- | - | $620 | 128 | - | - |
- - kWh |
$620 128 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED |
Savings: $548 Cost: - |
$548 | 8,499 | - | - | - | - |
$548 8,499 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $454 Cost: $300 |
$454 | 7,034 | - | - | - | - |
$454 7,034 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $183 Cost: - |
$38 | 586 | $145 | 30 | - | - |
$38 586 kWh |
$145 30 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $54,514 Cost: $9,770 |
$58,820 | 840,562 | $1,694 | 350 | $(-6,000) | - | $58,820 840,562 kWh |
$1,694 350 MMBtu |
$(-6,000) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $45,856 Cost: $5,920 |
$45,091 | 627,784 | $765 | 158 | - | - | $45,091 627,784 kWh |
$765 158 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |