Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Univ. of Kansas |
---|---|
Assessment Year | 1984 |
Principal Product | AVIATION ELECTRONICS |
NAICS | n/a |
SIC | 3699 - Electrical Equipment & Supplies, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 350 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 25,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | KS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $94,060 | 1,315,944 | kWh | $0.07 |
Natural Gas | $9,535 | 2,034 | MMBtu | $4.69 |
TOTAL ENERGY COSTS | $103,595 | |||
RECOMMENDED SAVINGS* | $32,527 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $18,351 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,910 Cost: $36 |
$4,910 | 68,875 | - | - | - | - |
$4,910 68,875 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $2,754 Cost: $3,000 |
$2,754 | - | - | - | - | - |
$2,754 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $514 Cost: $800 |
- | - | $572 | 122 | $(-58) | - |
- - kWh |
$572 122 MMBtu |
$(-58) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1123 INSTALL AUTOMATIC STACK DAMPER |
Savings: $436 Cost: $700 |
- | - | $436 | 93 | - | - |
- - kWh |
$436 93 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC |
Savings: $366 Cost: $100 |
- | - | $366 | 78 | - | - |
- - kWh |
$366 78 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $173 Cost: $70 |
$199 | 2,638 | $(-26) | (-5) | - | - |
$199 2,638 kWh |
$(-26) (-5) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,738 Cost: $1,240 |
$1,738 | 24,326 | - | - | - | - |
$1,738 24,326 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $99 Cost: $150 |
- | - | $159 | 34 | $(-60) | - |
- - kWh |
$159 34 MMBtu |
$(-60) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7441 REPLACE BROKEN WINDOWS AND/OR WINDOW SASH |
Savings: $298 Cost: $12 |
$21 | 293 | $277 | 59 | - | - |
$21 293 kWh |
$277 59 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7314 REDUCE VENTILATION AIR |
Savings: $2,954 Cost: $500 |
$(-1,089) | (-15,240) | $4,043 | 862 | - | - |
$(-1,089) (-15,240) kWh |
$4,043 862 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $10,658 Cost: $15,000 |
$10,658 | 149,179 | - | - | - | - |
$10,658 149,179 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $4,177 Cost: $17 |
$1,738 | 24,326 | $2,439 | 520 | - | - |
$1,738 24,326 kWh |
$2,439 520 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $1,182 Cost: $2,000 |
- | - | $1,182 | 252 | - | - |
- - kWh |
$1,182 252 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED |
Savings: $760 Cost: - |
$760 | 10,551 | - | - | - | - |
$760 10,551 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
15: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $1,508 Cost: $1,900 |
$2,094 | 29,308 | $(-586) | (-125) | - | - |
$2,094 29,308 kWh |
$(-586) (-125) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $32,527 Cost: $25,525 |
$23,783 | 294,256 | $8,862 | 1,890 | $(-118) | - | $23,783 294,256 kWh |
$8,862 1,890 MMBtu |
$(-118) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $18,351 Cost: $7,165 |
$9,094 | 88,805 | $9,315 | 1,986 | $(-58) | - | $9,094 88,805 kWh |
$9,315 1,986 MMBtu |
$(-58) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |