IAC Assessment: KU0239
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: KU0239
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Univ. of Kansas
Assessment Year 1987
Principal Product PRINTERS, BOOKS, PUBLICITY MATERIAL
NAICS n/a
SIC 2731 - Book Publishing
Sales $1,000,000-$5,000,000
# of Employees 60
Plant Area (Sq.Ft.) 0
Annual Production 756,000 Pieces
Production Hrs. Annual 1,820
Location (State) MO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $52,857 836,460 kWh $0.06
Natural Gas $8,538 2,332 MMBtu $3.66
TOTAL ENERGY COSTS $61,395
RECOMMENDED SAVINGS* $7,984 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $6,978
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$5,811
Cost:
$300
$3,096 48,945 $2,715 741 - - $3,096
48,945
kWh
$2,715
741
MMBtu
-
-
$
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$516
Cost:
-
$666 - - - $(-150) - $666
-
kWh
-
-
MMBtu
$(-150)
-
$
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$392
Cost:
-
- - $542 148 $(-150) - -
-
kWh
$542
148
MMBtu
$(-150)
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$410
Cost:
$79
$410 6,448 - - - - $410
6,448
kWh
-
-
MMBtu
-
-
$
05: 2.1222 INSTALL TURBULATORS Savings:
$318
Cost:
$500
- - $318 87 - - -
-
kWh
$318
87
MMBtu
-
-
$
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$222
Cost:
$50
$222 3,517 - - - - $222
3,517
kWh
-
-
MMBtu
-
-
$
07: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$172
Cost:
$50
- - $172 47 - - -
-
kWh
$172
47
MMBtu
-
-
$
08: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED Savings:
$143
Cost:
-
- - $143 39 - - -
-
kWh
$143
39
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$7,984
Cost:
$979
$4,394 58,910 $3,890 1,062 $(-300) - $4,394
58,910
kWh
$3,890
1,062
MMBtu
$(-300)
-
$
TOTAL IMPLEMENTED Savings:
$6,978
Cost:
$429
$3,728 58,910 $3,400 928 $(-150) - $3,728
58,910
kWh
$3,400
928
MMBtu
$(-150)
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes