Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Univ. of Kansas |
---|---|
Assessment Year | 1989 |
Principal Product | PRINTED LABELS |
NAICS | n/a |
SIC | 2759 - Commercial Printing, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 155 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 0 Units |
Production Hrs. Annual | 7,200 |
Location (State) | NE |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $76,282 | 1,601,993 | kWh | $0.05 |
Natural Gas | $13,132 | 3,401 | MMBtu | $3.86 |
TOTAL ENERGY COSTS | $89,414 | |||
RECOMMENDED SAVINGS* | $18,114 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $886 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $935 Cost: $462 |
$240 | 4,982 | $695 | 180 | - | - |
$240 4,982 kWh |
$695 180 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,133 Cost: $1,133 |
$1,133 | 23,740 | - | - | - | - |
$1,133 23,740 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $187 Cost: - |
$187 | 3,810 | - | - | - | - |
$187 3,810 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4312 IMPROVE LUBRICATION PRACTICES |
Savings: $167 Cost: - |
$167 | 3,517 | - | - | - | - |
$167 3,517 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $291 Cost: $350 |
$291 | 6,155 | - | - | - | - |
$291 6,155 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $1,986 Cost: $4,440 |
$1,986 | 41,618 | - | - | - | - |
$1,986 41,618 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.4156 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE |
Savings: $318 Cost: - |
- | - | - | - | $318 | - |
- - kWh |
- - MMBtu |
$318 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.5194 REDESIGN PROCESS |
Savings: $11,461 Cost: $13,200 |
$9,025 | 189,625 | - | - | $2,436 | - |
$9,025 189,625 kWh |
- - MMBtu |
$2,436 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED |
Savings: $241 Cost: - |
$192 | 4,103 | $49 | 13 | - | - |
$192 4,103 kWh |
$49 13 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $1,395 Cost: $2,300 |
$1,395 | 29,308 | - | - | - | - |
$1,395 29,308 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $18,114 Cost: $21,885 |
$14,616 | 306,858 | $744 | 193 | $2,754 | - | $14,616 306,858 kWh |
$744 193 MMBtu |
$2,754 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $886 Cost: $350 |
$837 | 17,585 | $49 | 13 | - | - | $837 17,585 kWh |
$49 13 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |