Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Univ. of Kansas |
---|---|
Assessment Year | 1992 |
Principal Product | INSTANT TEA |
NAICS | n/a |
SIC | 2087 - Flavoring Extracts And Syrups, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 40 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 4,800,000 Pounds |
Production Hrs. Annual | 5,592 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $839,433 | 18,896,249 | kWh | $0.04 |
Natural Gas | $801,358 | 318,063 | MMBtu | $2.52 |
TOTAL ENERGY COSTS | $1,640,791 | |||
RECOMMENDED SAVINGS* | $439,192 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $74,237 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2627 USE MULTIPLE-EFFECT EVAPORATORS |
Savings: $133,326 Cost: $720,000 |
- | - | $133,326 | 52,907 | - | - |
- - kWh |
$133,326 52,907 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $91,322 Cost: - |
$990 | 22,274 | - | - | $90,332 | - |
$990 22,274 kWh |
- - MMBtu |
$90,332 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $46,997 Cost: $208,233 |
$26,678 | 600,528 | $20,319 | 8,063 | - | - |
$26,678 600,528 kWh |
$20,319 8,063 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING |
Savings: $35,349 Cost: $117,700 |
$35,349 | 795,721 | - | - | - | - |
$35,349 795,721 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $29,723 Cost: $39,435 |
- | - | $29,723 | 11,795 | - | - |
- - kWh |
$29,723 11,795 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2444 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS |
Savings: $32,127 Cost: $90,000 |
- | - | $32,127 | 12,749 | - | - |
- - kWh |
$32,127 12,749 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2113 REPAIR OR REPLACE STEAM TRAPS |
Savings: $29,914 Cost: - |
- | - | $25,787 | 10,233 | $4,127 | - |
- - kWh |
$25,787 10,233 MMBtu |
$4,127 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $5,325 Cost: $670 |
- | - | $5,325 | 2,113 | - | - |
- - kWh |
$5,325 2,113 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $3,789 Cost: $10,400 |
$3,789 | 85,287 | - | - | - | - |
$3,789 85,287 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $17,785 Cost: $70,400 |
$17,785 | 400,352 | - | - | - | - |
$17,785 400,352 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY |
Savings: $6,367 Cost: $8,000 |
$6,367 | 143,318 | - | - | - | - |
$6,367 143,318 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $4,086 Cost: - |
$2,357 | 53,048 | $1,729 | 686 | - | - |
$2,357 53,048 kWh |
$1,729 686 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $3,082 Cost: $10,685 |
- | - | $3,082 | 1,223 | - | - |
- - kWh |
$3,082 1,223 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $439,192 Cost: $1,275,523 |
$93,315 | 2,100,528 | $251,418 | 99,769 | $94,459 | - | $93,315 2,100,528 kWh |
$251,418 99,769 MMBtu |
$94,459 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $74,237 Cost: $111,755 |
$3,789 | 85,287 | $66,321 | 26,318 | $4,127 | - | $3,789 85,287 kWh |
$66,321 26,318 MMBtu |
$4,127 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |