Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Univ. of Kansas |
---|---|
Assessment Year | 1994 |
Principal Product | antennas |
NAICS | n/a |
SIC | 3663 - Radio & Tv Communications Equipment |
Sales | $10,000,000-$50,000,000 |
# of Employees | 340 |
Plant Area (Sq.Ft.) | 165,000 |
Annual Production | 82,500 Pieces |
Production Hrs. Annual | 4,400 |
Location (State) | NE |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $131,103 | 2,755,276 | kWh | $0.05 |
Natural Gas | $35,463 | 9,676 | MMBtu | $3.67 |
TOTAL ENERGY COSTS | $166,566 | |||
RECOMMENDED SAVINGS* | $55,160 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $14,283 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $6,218 Cost: $300 |
- | - | - | - | $6,218 | - |
- - kWh |
- - MMBtu |
$6,218 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3134 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION |
Savings: $17,492 Cost: $1,000 |
$17,492 | - | - | - | - | - |
$17,492 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $7,856 Cost: $29,000 |
$19,181 | 402,989 | $(-11,325) | (-3,086) | - | - |
$19,181 402,989 kWh |
$(-11,325) (-3,086) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $7,795 Cost: $10,100 |
- | - | $7,795 | 2,124 | - | - |
- - kWh |
$7,795 2,124 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $3,951 Cost: $1,130 |
$2,288 | 48,066 | $1,663 | 453 | - | - |
$2,288 48,066 kWh |
$1,663 453 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $3,050 Cost: $825 |
$195 | 4,103 | $2,855 | 778 | - | - |
$195 4,103 kWh |
$2,855 778 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $460 Cost: $1,466 |
$460 | 9,672 | - | - | - | - |
$460 9,672 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $2,090 Cost: $2,363 |
$2,090 | 23,740 | - | - | - | - |
$2,090 23,740 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $837 Cost: $1,486 |
$1,200 | 25,205 | $(-363) | (-99) | - | - |
$1,200 25,205 kWh |
$(-363) (-99) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $3,404 Cost: $888 |
$3,404 | 71,512 | - | - | - | - |
$3,404 71,512 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,297 Cost: $2,487 |
$1,297 | 27,257 | - | - | - | - |
$1,297 27,257 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $258 Cost: $360 |
$258 | 1,172 | - | - | - | - |
$258 1,172 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $452 Cost: $582 |
$452 | 5,275 | - | - | - | - |
$452 5,275 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $55,160 Cost: $51,987 |
$48,317 | 618,991 | $625 | 170 | $6,218 | - | $48,317 618,991 kWh |
$625 170 MMBtu |
$6,218 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $14,283 Cost: $3,260 |
$6,402 | 126,025 | $1,663 | 453 | $6,218 | - | $6,402 126,025 kWh |
$1,663 453 MMBtu |
$6,218 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |