IAC logo
IAC Assessment: LE0225
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: LE0225
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Lehigh University
Assessment Year 2005
Principal Product Metal cutting saw blades
NAICS 332216 - Saw Blade and Handtool Manufacturing
SIC 2425 -
Sales $1,000,000-$5,000,000
# of Employees 26
Plant Area (Sq.Ft.) 129,213
Annual Production 8,722 Tons
Production Hrs. Annual 4,000
Location (State) PA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $120,292 1,392,000 kWh $0.09
Electricity Demand $23,364 3,881 kW-months/year $6.02
Natural Gas $231,376 22,089 MMBtu $10.47
TOTAL ENERGY COSTS $375,032
RECOMMENDED SAVINGS* $76,406 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $31,769
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Electricity Usage Electricity Demand Natural Gas Personnel Changes
$ kWh $ kW-months/year $ MMBtu $ $
01: 4.4450 INSTALL EQUIPMENT TO MOVE PRODUCT Savings:
$28,200
Cost:
$2,000
- - - - - - $28,200 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$28,200
-
$
02: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC Savings:
$17,500
Cost:
$50,000
- - - - $17,500 1,671 - - -
-
kWh
-
-
kW-months/year
$17,500
1,671
MMBtu
-
-
$
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$11,161
Cost:
$2,800
- - - - $11,161 1,066 - - -
-
kWh
-
-
kW-months/year
$11,161
1,066
MMBtu
-
-
$
04: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$5,707
Cost:
$200
- - $5,707 948 - - - - -
-
kWh
$5,707
948
kW-months/year
-
-
MMBtu
-
-
$
05: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$4,158
Cost:
$800
$3,436 39,948 $722 120 - - - - $3,436
39,948
kWh
$722
120
kW-months/year
-
-
MMBtu
-
-
$
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,558
Cost:
$100
$2,114 24,584 $444 74 - - - - $2,114
24,584
kWh
$444
74
kW-months/year
-
-
MMBtu
-
-
$
07: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC Savings:
$1,914
Cost:
$2,500
- - - - $1,914 183 - - -
-
kWh
-
-
kW-months/year
$1,914
183
MMBtu
-
-
$
08: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$1,118
Cost:
$350
$924 10,742 $194 32 - - - - $924
10,742
kWh
$194
32
kW-months/year
-
-
MMBtu
-
-
$
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,090
Cost:
$35,595
$3,151 36,640 $939 156 - - - - $3,151
36,640
kWh
$939
156
kW-months/year
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$76,406
Cost:
$94,345
$9,625 111,914 $8,006 1,330 $30,575 2,920 $28,200 - $9,625
111,914
kWh
$8,006
1,330
kW-months/year
$30,575
2,920
MMBtu
$28,200
-
$
TOTAL IMPLEMENTED Savings:
$31,769
Cost:
$88,395
$5,265 61,224 $7,090 1,178 $19,414 1,854 - - $5,265
61,224
kWh
$7,090
1,178
kW-months/year
$19,414
1,854
MMBtu
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Electricity Usage Electricity Demand Natural Gas Personnel Changes