Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Lehigh University |
---|---|
Assessment Year | 2008 |
Principal Product | Precision Machined Parts |
NAICS | 332721 - Precision Turned Product Manufacturing |
SIC | 3451 - Screw Machine Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 172 |
Plant Area (Sq.Ft.) | 70,000 |
Annual Production | 20,400,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $239,298 | 3,859,200 | kWh | $0.06 |
Electricity Demand | $73,746 | 8,478 | kW-months/year | $8.70 |
Natural Gas | $11,369 | 731 | MMBtu | $15.55 |
LPG | $2,890 | 95 | MMBtu | $30.42 |
TOTAL ENERGY COSTS | $327,303 | |||
RECOMMENDED SAVINGS* | $106,852 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $43,331 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $22,241 Cost: $20,000 |
$17,517 | 282,538 | $4,724 | 543 | - | - | - | - | - | - |
$17,517 282,538 kWh |
$4,724 543 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $16,646 Cost: $6,020 |
$16,646 | 268,488 | - | - | - | - | - | - | - | - |
$16,646 268,488 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $12,225 Cost: $1,800 |
$9,406 | 151,710 | $2,819 | 324 | - | - | - | - | - | - |
$9,406 151,710 kWh |
$2,819 324 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $9,912 Cost: $5,250 |
- | - | - | - | - | - | $9,912 | 637 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$9,912 637 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $9,781 Cost: $2,200 |
$1,835 | 29,593 | - | - | $(-223) | - | $8,169 | 525 | - | - |
$1,835 29,593 kWh |
- - kW-months/year |
$(-223) - $ |
$8,169 525 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,675 Cost: $1,000 |
$5,257 | 84,787 | $1,418 | 163 | - | - | - | - | - | - |
$5,257 84,787 kWh |
$1,418 163 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,495 Cost: $11,500 |
$4,329 | 69,825 | $1,166 | 134 | - | - | - | - | - | - |
$4,329 69,825 kWh |
$1,166 134 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $5,121 Cost: $300 |
$5,121 | 82,595 | - | - | - | - | - | - | - | - |
$5,121 82,595 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $2,949 Cost: $4,000 |
- | - | $2,949 | 339 | - | - | - | - | - | - |
- - kWh |
$2,949 339 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,664 Cost: $50 |
$2,046 | 33,004 | $618 | 71 | - | - | - | - | - | - |
$2,046 33,004 kWh |
$618 71 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $13,143 Cost: $47,522 |
$8,688 | 140,132 | $2,349 | 270 | - | - | - | - | $2,106 | - |
$8,688 140,132 kWh |
$2,349 270 kW-months/year |
- - $ |
- - MMBtu |
$2,106 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $106,852 Cost: $99,642 |
$70,845 | 1,142,672 | $16,043 | 1,844 | $(-223) | - | $18,081 | 1,162 | $2,106 | - | $70,845 1,142,672 kWh |
$16,043 1,844 kW-months/year |
$(-223) - $ |
$18,081 1,162 MMBtu |
$2,106 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $43,331 Cost: $9,170 |
$38,476 | 620,584 | $4,855 | 558 | - | - | - | - | - | - | $38,476 620,584 kWh |
$4,855 558 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Ancillary Material Cost |