Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Louisiana, Lafayette |
---|---|
Assessment Year | 2003 |
Principal Product | Natural Gas Purification |
NAICS | 324110 - Petroleum Refineries |
SIC | 2911 - Petroleum Refining |
Sales | $100,000,000-$500,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 2,100,000 |
Annual Production | 73,000 Units |
Production Hrs. Annual | 2,860 |
Location (State) | LA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $532,474 | 16,830,000 | kWh | $0.03 |
Electricity Demand | $266,833 | 30,483 | kW-months/year | $8.75 |
Electricity Fees | $86,889 | - | $ | - |
Natural Gas | $110,260 | 31,503 | MMBtu | $3.50 |
TOTAL ENERGY COSTS | $996,456 | |||
RECOMMENDED SAVINGS* | $193,496 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $172,842 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1336 INSTALL EQUIPMENT TO UTILIZE WASTE FUEL |
Savings: $100,695 Cost: $120,000 |
- | - | - | - | - | - | $100,695 | 28,770 |
- - kWh |
- - kW-months/year |
- - $ |
$100,695 28,770 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $16,855 Cost: $9,440 |
$16,207 | 509,960 | - | - | $648 | - | - | - |
$16,207 509,960 kWh |
- - kW-months/year |
$648 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $9,566 Cost: $3,733 |
- | - | - | - | - | - | $9,566 | 2,733 |
- - kWh |
- - kW-months/year |
- - $ |
$9,566 2,733 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $7,286 Cost: $20 |
$4,757 | 149,671 | $2,249 | 257 | $280 | - | - | - |
$4,757 149,671 kWh |
$2,249 257 kW-months/year |
$280 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $1,918 Cost: $492 |
$1,266 | 39,836 | $578 | 66 | $74 | - | - | - |
$1,266 39,836 kWh |
$578 66 kW-months/year |
$74 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $967 Cost: $570 |
$589 | 18,540 | $341 | 39 | $37 | - | - | - |
$589 18,540 kWh |
$341 39 kW-months/year |
$37 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $917 Cost: $572 |
$339 | 10,663 | $543 | 62 | $35 | - | - | - |
$339 10,663 kWh |
$543 62 kW-months/year |
$35 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $55,292 Cost: - |
- | - | - | - | $55,292 | - | - | - |
- - kWh |
- - kW-months/year |
$55,292 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $193,496 Cost: $134,827 |
$23,158 | 728,670 | $3,711 | 424 | $56,366 | - | $110,261 | 31,503 | $23,158 728,670 kWh |
$3,711 424 kW-months/year |
$56,366 - $ |
$110,261 31,503 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $172,842 Cost: $129,440 |
$16,207 | 509,960 | - | - | $55,940 | - | $100,695 | 28,770 | $16,207 509,960 kWh |
- - kW-months/year |
$55,940 - $ |
$100,695 28,770 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas |