Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Louisiana, Lafayette |
---|---|
Assessment Year | 2005 |
Principal Product | Rice |
NAICS | 311212 - Rice Milling |
SIC | 2044 - Rice Milling |
Sales | $50,000,000-$100,000,000 |
# of Employees | 71 |
Plant Area (Sq.Ft.) | 60,000 |
Annual Production | 3,875,000 Tons |
Production Hrs. Annual | 7,440 |
Location (State) | LA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $703,285 | 12,787,000 | kWh | $0.06 |
Electricity Fees | $28,131 | - | $ | - |
TOTAL ENERGY COSTS | $731,416 | |||
RECOMMENDED SAVINGS* | $93,442 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $28,925 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Personnel Changes | Electricity Usage | Electricity Fees | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $15,480 Cost: $11,450 |
$14,885 | 270,639 | $595 | - | - | - |
$14,885 270,639 kWh |
$595 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $9,239 Cost: $2,920 |
$8,884 | 161,529 | $355 | - | - | - |
$8,884 161,529 kWh |
$355 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,479 Cost: $30 |
$2,384 | 43,348 | $95 | - | - | - |
$2,384 43,348 kWh |
$95 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $2,331 Cost: $300 |
$2,241 | 40,751 | $90 | - | - | - |
$2,241 40,751 kWh |
$90 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,514 Cost: $300 |
$1,456 | 26,477 | $58 | - | - | - |
$1,456 26,477 kWh |
$58 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $1,381 Cost: $180 |
$1,328 | 24,138 | $53 | - | - | - |
$1,328 24,138 kWh |
$53 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $524 Cost: $330 |
$504 | 9,158 | $20 | - | - | - |
$504 9,158 kWh |
$20 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $494 Cost: $350 |
$183 | 3,329 | $7 | - | $304 | - |
$183 3,329 kWh |
$7 - $ |
$304 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2693 USE WASTE HEAT STEAM FOR ABSORPTION REFRIGERATION |
Savings: $60,000 Cost: $41,000 |
- | - | - | - | $60,000 | - |
- - kWh |
- - $ |
$60,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $93,442 Cost: $56,860 |
$31,865 | 579,369 | $1,273 | - | $60,304 | - | $31,865 579,369 kWh |
$1,273 - $ |
$60,304 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $28,925 Cost: $15,200 |
$27,521 | 500,386 | $1,100 | - | $304 | - | $27,521 500,386 kWh |
$1,100 - $ |
$304 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Personnel Changes | Electricity Usage | Electricity Fees | Personnel Changes |