IAC Assessment: LL0272
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: LL0272
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Louisiana, Lafayette
Assessment Year 2007
Principal Product Glassware
NAICS 327212 - Other Pressed and Blown Glass and Glassware Manufacturing
SIC 3229 - Pressed And Blown Glass, Nec
Sales $100,000,000-$500,000,000
# of Employees 1,000
Plant Area (Sq.Ft.) 500,000
Annual Production 200,000,000 Pieces
Production Hrs. Annual 8,400
Location (State) LA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,639,601 62,355,601 kWh $0.03
Electricity Demand $983,336 96,118 kW-months/year $10.23
Electricity Fees $86,557 - $ -
Natural Gas $10,169,864 1,457,087 MMBtu $6.98
TOTAL ENERGY COSTS $12,879,358
RECOMMENDED SAVINGS* $184,290 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $58,782
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes
$ kWh $ kW-months/year $ $ $ MMBtu $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$102,410
Cost:
$49,360
$63,718 2,423,646 $35,420 3,462 $3,272 - - - - - $63,718
2,423,646
kWh
$35,420
3,462
kW-months/year
$3,272
-
$
-
-
MMBtu
-
-
$
02: 2.2511 INSULATE BARE EQUIPMENT Savings:
$58,782
Cost:
$19,636
- - - - - - $58,782 8,423 - - -
-
kWh
-
-
kW-months/year
-
-
$
$58,782
8,423
MMBtu
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$8,485
Cost:
$7,000
$1,678 63,840 $897 88 $87 - - - $5,823 - $1,678
63,840
kWh
$897
88
kW-months/year
$87
-
$
-
-
MMBtu
$5,823
-
$
04: 2.4222 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN Savings:
$7,489
Cost:
$422
$4,660 177,254 $2,590 253 $239 - - - - - $4,660
177,254
kWh
$2,590
253
kW-months/year
$239
-
$
-
-
MMBtu
-
-
$
05: 2.7145 INSTALL SKYLIGHTS Savings:
$2,828
Cost:
$5,040
$2,738 104,160 - - $90 - - - - - $2,738
104,160
kWh
-
-
kW-months/year
$90
-
$
-
-
MMBtu
-
-
$
06: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$1,024
Cost:
$1,499
$991 37,701 - - $33 - - - - - $991
37,701
kWh
-
-
kW-months/year
$33
-
$
-
-
MMBtu
-
-
$
07: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$832
Cost:
$830
$263 10,006 $542 53 $27 - - - - - $263
10,006
kWh
$542
53
kW-months/year
$27
-
$
-
-
MMBtu
-
-
$
08: 2.6211 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES Savings:
$1,020
Cost:
$2,338
$643 24,461 $344 34 $33 - - - - - $643
24,461
kWh
$344
34
kW-months/year
$33
-
$
-
-
MMBtu
-
-
$
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$903
Cost:
$1,169
$562 21,363 $312 31 $29 - - - - - $562
21,363
kWh
$312
31
kW-months/year
$29
-
$
-
-
MMBtu
-
-
$
10: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$517
Cost:
$5,436
$499 18,994 - - $18 - - - - - $499
18,994
kWh
-
-
kW-months/year
$18
-
$
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$184,290
Cost:
$92,730
$75,752 2,881,425 $40,105 3,921 $3,828 - $58,782 8,423 $5,823 - $75,752
2,881,425
kWh
$40,105
3,921
kW-months/year
$3,828
-
$
$58,782
8,423
MMBtu
$5,823
-
$
TOTAL IMPLEMENTED Savings:
$58,782
Cost:
$19,636
- - - - - - $58,782 8,423 - - -
-
kWh
-
-
kW-months/year
-
-
$
$58,782
8,423
MMBtu
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes