Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Loyola Marymount University |
---|---|
Assessment Year | 2002 |
Principal Product | metal stampings |
NAICS | n/a |
SIC | 3484 - Small Arms |
Sales | $1,000,000-$5,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 38,000 |
Annual Production | 60,000,000 Pieces |
Production Hrs. Annual | 2,600 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $55,662 | 539,958 | kWh | $0.10 |
Electricity Demand | $32,413 | 3,996 | kW-months/year | $8.11 |
Electricity Fees | $5,375 | - | $ | - |
Natural Gas | $4,993 | 515 | MMBtu | $9.70 |
TOTAL ENERGY COSTS | $98,443 | |||
RECOMMENDED SAVINGS* | $40,037 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $20,000 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,575 Cost: $2,880 |
$1,228 | 10,264 | $347 | 43 | - | - | - | - |
$1,228 10,264 kWh |
$347 43 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,338 Cost: $550 |
$3,773 | 31,542 | $1,345 | 168 | $(-780) | - | - | - |
$3,773 31,542 kWh |
$1,345 168 kW-months/year |
$(-780) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $211 Cost: $228 |
$161 | 1,350 | $50 | 6 | - | - | - | - |
$161 1,350 kWh |
$50 6 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,154 Cost: - |
$883 | 7,378 | $271 | 34 | - | - | - | - |
$883 7,378 kWh |
$271 34 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS |
Savings: $2,496 Cost: $900 |
- | - | - | - | $2,496 | - | - | - |
- - kWh |
- - kW-months/year |
$2,496 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $20,000 Cost: $600 |
- | - | - | - | $20,000 | - | - | - |
- - kWh |
- - kW-months/year |
$20,000 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.454 MODIFY STARTUP/SHUTDOWN TIMES |
Savings: $10,263 Cost: $300 |
- | - | $8,003 | - | $(-4,500) | - | $6,760 | - |
- - kWh |
$8,003 - kW-months/year |
$(-4,500) - $ |
$6,760 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $40,037 Cost: $5,458 |
$6,045 | 50,534 | $10,016 | 251 | $17,216 | - | $6,760 | - | $6,045 50,534 kWh |
$10,016 251 kW-months/year |
$17,216 - $ |
$6,760 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $20,000 Cost: $600 |
- | - | - | - | $20,000 | - | - | - | - - kWh |
- - kW-months/year |
$20,000 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes |