Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Louisiana Tech |
---|---|
Assessment Year | 1988 |
Principal Product | CONVERTED PAPER |
NAICS | n/a |
SIC | 2679 - Converted Paper Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 88 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 68,000 Tons |
Production Hrs. Annual | 6,000 |
Location (State) | LA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $231,768 | 4,427,902 | kWh | $0.05 |
Natural Gas | $5,796 | 3,057 | MMBtu | $1.90 |
TOTAL ENERGY COSTS | $237,564 | |||
RECOMMENDED SAVINGS* | $11,127 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $9,541 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $340 Cost: $5,000 |
- | - | $340 | 179 | - | - |
- - kWh |
$340 179 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7229 AIR CONDITION ONLY SPACE NECESSARY |
Savings: $2,754 Cost: - |
$1,466 | 35,756 | $1,288 | 678 | - | - |
$1,466 35,756 kWh |
$1,288 678 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $345 Cost: - |
$345 | 8,499 | - | - | - | - |
$345 8,499 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $3,315 Cost: - |
$3,315 | 80,891 | - | - | - | - |
$3,315 80,891 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $183 Cost: $118 |
$208 | 4,103 | - | - | $(-25) | - |
$208 4,103 kWh |
- - MMBtu |
$(-25) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,177 Cost: $475 |
$992 | 21,981 | - | - | $185 | - |
$992 21,981 kWh |
- - MMBtu |
$185 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $716 Cost: $315 |
$980 | 24,033 | - | - | $(-264) | - |
$980 24,033 kWh |
- - MMBtu |
$(-264) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $365 Cost: - |
$365 | 8,792 | - | - | - | - |
$365 8,792 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $564 Cost: $890 |
$564 | 12,309 | - | - | - | - |
$564 12,309 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $185 Cost: $69 |
$85 | 13,189 | $100 | 52 | - | - |
$85 13,189 kWh |
$100 52 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $313 Cost: $50 |
$313 | 7,620 | - | - | - | - |
$313 7,620 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $870 Cost: $2,000 |
$992 | 17,878 | $(-122) | (-64) | - | - |
$992 17,878 kWh |
$(-122) (-64) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $11,127 Cost: $8,917 |
$9,625 | 235,051 | $1,606 | 845 | $(-104) | - | $9,625 235,051 kWh |
$1,606 845 MMBtu |
$(-104) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $9,541 Cost: $6,602 |
$7,653 | 193,140 | $1,728 | 909 | $160 | - | $7,653 193,140 kWh |
$1,728 909 MMBtu |
$160 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |