IAC Assessment: LT8363
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Louisiana Tech
Assessment Year 2022
Principal Product Bread products
NAICS 311812 - Commercial Bakeries
SIC 2051 - Bread, Cake, And Related Products
Sales $100,000,000-$500,000,000
# of Employees 100
Plant Area (Sq.Ft.) 53,600
Annual Production 30,000,000 Units
Production Hrs. Annual 7,500
Location (State) AR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $436,000 5,004,300 kWh $0.09
Electricity Demand $124,619 8,801 kW-months/year $14.16
Natural Gas $27,810 2,189 MMBtu $12.70
LPG $620 20 MMBtu $31.20
TOTAL ENERGY COSTS $610,384
RECOMMENDED SAVINGS* $138,991 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ $ $ $
01: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$5,980
Cost:
$10,022
- - - - $5,980 - - - - - - - -
-
kWh
-
-
kW-months/year
$5,980
-
$
-
-
MMBtu
-
-
$
-
-
$
02: 4.632 CHANGE OPERATING CONDITIONS Savings:
$46,622
Cost:
-
- - - - - - - - $46,622 - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$46,622
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$24,542
Cost:
$2,945
$3,623 41,507 $20,919 1,477 - - - - - - - - $3,623
41,507
kWh
$20,919
1,477
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
$
04: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS Savings:
$14,468
Cost:
$15,975
- - - - - - - - - - $14,468 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
$14,468
-
$
05: 2.7425 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD Savings:
$22,308
Cost:
$32,500
$18,400 211,000 $3,908 276 - - - - - - - - $18,400
211,000
kWh
$3,908
276
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
$
06: 2.2441 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT Savings:
$23,817
Cost:
$51,385
- - - - - - $23,817 1,875 - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$23,817
1,875
MMBtu
-
-
$
-
-
$
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,254
Cost:
-
$1,016 11,633 $238 17 - - - - - - - - $1,016
11,633
kWh
$238
17
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$138,991
Cost:
$112,827
$23,039 264,141 $25,065 1,770 $5,980 - $23,817 1,875 $46,622 - $14,468 - $23,039
264,141
kWh
$25,065
1,770
kW-months/year
$5,980
-
$
$23,817
1,875
MMBtu
$46,622
-
$
$14,468
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes Ancillary Material Cost