Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1987 |
Principal Product | ARCHITECTURAL PRODUCTS |
NAICS | n/a |
SIC | 3446 - Architectural Metal Work |
Sales | $5,000,000-$10,000,000 |
# of Employees | 90 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 7,000,000 Pounds |
Production Hrs. Annual | 5,760 |
Location (State) | CT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $231,934 | 1,905,920 | kWh | $0.12 |
Natural Gas | $27,796 | 6,982 | MMBtu | $3.98 |
Fuel Oil #2 | $4,000 | 896 | MMBtu | $4.46 |
Fuel Oil #6 | $22,600 | 6,810 | MMBtu | $3.32 |
TOTAL ENERGY COSTS | $286,330 | |||
RECOMMENDED SAVINGS* | $40,791 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $40,791 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $17,912 Cost: $12,250 |
$17,912 | 147,128 | - | - | - | - |
$17,912 147,128 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES |
Savings: $219 Cost: $132 |
- | - | $219 | 55 | - | - |
- - kWh |
$219 55 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,084 Cost: $1,890 |
- | - | $1,084 | 271 | - | - |
- - kWh |
$1,084 271 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $21,576 Cost: $62,000 |
$27,648 | 230,363 | $(-3,072) | (-768) | $(-3,000) | - |
$27,648 230,363 kWh |
$(-3,072) (-768) MMBtu |
$(-3,000) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $40,791 Cost: $76,272 |
$45,560 | 377,491 | $(-1,769) | (-442) | $(-3,000) | - | $45,560 377,491 kWh |
$(-1,769) (-442) MMBtu |
$(-3,000) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $40,791 Cost: $76,272 |
$45,560 | 377,491 | $(-1,769) | (-442) | $(-3,000) | - | $45,560 377,491 kWh |
$(-1,769) (-442) MMBtu |
$(-3,000) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |