Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1987 |
Principal Product | METAL PLATING OF SURFACE |
NAICS | n/a |
SIC | 3471 - Plating And Polishing |
Sales | $5,000,000-$10,000,000 |
# of Employees | 76 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 0 Units |
Production Hrs. Annual | 4,000 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $87,462 | 1,483,880 | kWh | $0.06 |
Natural Gas | $64,755 | 15,379 | MMBtu | $4.21 |
Fuel Oil #2 | $32,578 | 8,414 | MMBtu | $3.87 |
TOTAL ENERGY COSTS | $184,795 | |||
RECOMMENDED SAVINGS* | $26,465 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $18,004 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Fuel Oil #2 | Electricity Usage | Natural Gas | Fuel Oil #2 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $977 Cost: $116 |
$977 | 16,413 | - | - | - | - |
$977 16,413 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,853 Cost: $2,000 |
$3,853 | 65,358 | - | - | - | - |
$3,853 65,358 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $3,607 Cost: $4,400 |
- | - | - | - | $3,607 | 932 |
- - kWh |
- - MMBtu |
$3,607 932 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $5,581 Cost: $10,000 |
$5,581 | 94,666 | - | - | - | - |
$5,581 94,666 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $2,880 Cost: $3,100 |
- | - | $2,880 | 684 | - | - |
- - kWh |
$2,880 684 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $4,113 Cost: $2,238 |
- | - | $4,113 | 977 | - | - |
- - kWh |
$4,113 977 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2514 COVER OPEN TANKS |
Savings: $3,570 Cost: $1,122 |
- | - | $3,570 | 848 | - | - |
- - kWh |
$3,570 848 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,884 Cost: $1,333 |
$1,884 | 31,946 | - | - | - | - |
$1,884 31,946 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $26,465 Cost: $24,309 |
$12,295 | 208,383 | $10,563 | 2,509 | $3,607 | 932 | $12,295 208,383 kWh |
$10,563 2,509 MMBtu |
$3,607 932 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $18,004 Cost: $11,209 |
$6,714 | 113,717 | $7,683 | 1,825 | $3,607 | 932 | $6,714 113,717 kWh |
$7,683 1,825 MMBtu |
$3,607 932 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Fuel Oil #2 | Electricity Usage | Natural Gas | Fuel Oil #2 |