Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1989 |
Principal Product | FLUID MILK PRODUCTS |
NAICS | n/a |
SIC | 2026 - Fluid Milk |
Sales | $10,000,000-$50,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 20,000 Thousand Gallons |
Production Hrs. Annual | 7,344 |
Location (State) | CT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $331,966 | 5,096,131 | kWh | $0.07 |
Natural Gas | $54,082 | 15,516 | MMBtu | $3.49 |
Fuel Oil #2 | $13,604 | 2,881 | MMBtu | $4.72 |
TOTAL ENERGY COSTS | $399,652 | |||
RECOMMENDED SAVINGS* | $32,187 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,703 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Fuel Oil #2 | Administrative Changes | Electricity Usage | Natural Gas | Fuel Oil #2 | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $632 Cost: $217 |
$632 | 9,672 | - | - | - | - | - | - |
$632 9,672 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $878 Cost: $163 |
$878 | 13,482 | - | - | - | - | - | - |
$878 13,482 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,825 Cost: $500 |
$2,209 | 33,998 | - | - | - | - | $1,616 | - |
$2,209 33,998 kWh |
- - MMBtu |
- - MMBtu |
$1,616 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3416 USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST |
Savings: $19,722 Cost: $115,000 |
$36,262 | 550,703 | $(-7,360) | (-2,112) | - | - | $(-9,180) | - |
$36,262 550,703 kWh |
$(-7,360) (-2,112) MMBtu |
- - MMBtu |
$(-9,180) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $3,985 Cost: $1,910 |
$3,985 | - | - | - | - | - | - | - |
$3,985 - kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC |
Savings: $530 Cost: $218 |
- | - | $423 | 121 | $107 | 23 | - | - |
- - kWh |
$423 121 MMBtu |
$107 23 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $2,615 Cost: $3,000 |
$2,615 | 40,152 | - | - | - | - | - | - |
$2,615 40,152 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $32,187 Cost: $121,008 |
$46,581 | 648,007 | $(-6,937) | (-1,991) | $107 | 23 | $(-7,564) | - | $46,581 648,007 kWh |
$(-6,937) (-1,991) MMBtu |
$107 23 MMBtu |
$(-7,564) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,703 Cost: $663 |
$3,087 | 47,480 | - | - | - | - | $1,616 | - | $3,087 47,480 kWh |
- - MMBtu |
- - MMBtu |
$1,616 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Fuel Oil #2 | Administrative Changes | Electricity Usage | Natural Gas | Fuel Oil #2 | Administrative Changes |