Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1992 |
Principal Product | SPECIALTY PAPER |
NAICS | n/a |
SIC | 2679 - Converted Paper Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 122 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 12,000 Tons |
Production Hrs. Annual | 6,120 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $639,601 | 8,295,721 | kWh | $0.08 |
Natural Gas | $90,917 | 15,818 | MMBtu | $5.75 |
Fuel Oil #6 | $547,059 | 196,399 | MMBtu | $2.79 |
TOTAL ENERGY COSTS | $1,277,577 | |||
RECOMMENDED SAVINGS* | $146,452 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $17,256 |
#|Description |
Savings Cost |
Status | Electricity Usage | Fuel Oil #6 | Administrative Changes | Electricity Usage | Fuel Oil #6 | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2444 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS |
Savings: $95,745 Cost: $229,893 |
$(-8,023) | (-104,045) | $103,768 | 37,193 | - | - |
$(-8,023) (-104,045) kWh |
$103,768 37,193 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $13,364 Cost: $30,000 |
- | - | $13,364 | 4,790 | - | - |
- - kWh |
$13,364 4,790 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $5,409 Cost: $2,790 |
- | - | $5,409 | 1,939 | - | - |
- - kWh |
$5,409 1,939 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED |
Savings: $3,499 Cost: $11,534 |
- | - | $3,499 | 1,254 | - | - |
- - kWh |
$3,499 1,254 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $13,256 Cost: $36 |
$13,752 | 178,781 | - | - | $(-496) | - |
$13,752 178,781 kWh |
- - MMBtu |
$(-496) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $7,652 Cost: $20,657 |
$7,652 | 99,062 | - | - | - | - |
$7,652 99,062 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $4,000 Cost: - |
$4,000 | 51,876 | - | - | - | - |
$4,000 51,876 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,209 Cost: $11,204 |
$3,209 | 41,618 | - | - | - | - |
$3,209 41,618 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES |
Savings: $318 Cost: $740 |
- | - | $318 | 114 | - | - |
- - kWh |
$318 114 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $146,452 Cost: $306,854 |
$20,590 | 267,292 | $126,358 | 45,290 | $(-496) | - | $20,590 267,292 kWh |
$126,358 45,290 MMBtu |
$(-496) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $17,256 Cost: $36 |
$17,752 | 230,657 | - | - | $(-496) | - | $17,752 230,657 kWh |
- - MMBtu |
$(-496) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Fuel Oil #6 | Administrative Changes | Electricity Usage | Fuel Oil #6 | Administrative Changes |