IAC Assessment: MA0238
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0238
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 1992
Principal Product INJECTION MOLDED PLASTIC
NAICS n/a
SIC 3089 - Plastics Products, Nec
Sales $5,000,000-$10,000,000
# of Employees 57
Plant Area (Sq.Ft.) 0
Annual Production 750,000 Pounds
Production Hrs. Annual 8,544
Location (State) CT
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $351,628 4,560,082 kWh $0.08
Natural Gas $4,949 661 MMBtu $7.49
TOTAL ENERGY COSTS $356,577
RECOMMENDED SAVINGS* $67,539 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $11,300
#|Description Savings
Cost
Status Electricity Usage Administrative Changes Electricity Usage Administrative Changes
$ kWh $ $
01: 2.2211 USE OPTIMUM TEMPERATURE Savings:
$22,238
Cost:
$2,775
$22,238 288,394 - - $22,238
288,394
kWh
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,104
Cost:
-
$3,600 46,600 $(-496) - $3,600
46,600
kWh
$(-496)
-
$
03: 2.2511 INSULATE BARE EQUIPMENT Savings:
$11,684
Cost:
$787
$11,684 151,524 - - $11,684
151,524
kWh
-
-
$
04: 2.6241 REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY Savings:
$10,215
Cost:
$31,246
$10,215 132,474 - - $10,215
132,474
kWh
-
-
$
05: 2.6241 REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY Savings:
$8,950
Cost:
$27,957
$8,950 116,061 - - $8,950
116,061
kWh
-
-
$
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$8,814
Cost:
$2,053
$8,814 114,302 - - $8,814
114,302
kWh
-
-
$
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$2,305
Cost:
-
$2,305 29,894 - - $2,305
29,894
kWh
-
-
$
08: 2.2611 MODERATE COOLING TOWER OUTLET TEMPERATURE Savings:
$181
Cost:
$100
$181 2,345 - - $181
2,345
kWh
-
-
$
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$48
Cost:
-
$48 4,103 - - $48
4,103
kWh
-
-
$
TOTAL RECOMMENDED Savings:
$67,539
Cost:
$64,918
$68,035 885,697 $(-496) - $68,035
885,697
kWh
$(-496)
-
$
TOTAL IMPLEMENTED Savings:
$11,300
Cost:
$2,153
$11,300 146,541 - - $11,300
146,541
kWh
-
-
$
Savings
Cost
$ kWh $ $
Electricity Usage Administrative Changes Electricity Usage Administrative Changes