Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1995 |
Principal Product | metal coating services |
NAICS | n/a |
SIC | 3479 - Metal Coating And Allied Services |
Sales | $1,000,000-$5,000,000 |
# of Employees | 37 |
Plant Area (Sq.Ft.) | 52,500 |
Annual Production | 0 Units |
Production Hrs. Annual | 2,250 |
Location (State) | CT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $105,315 | 701,055 | kWh | $0.15 |
Natural Gas | $126,979 | 15,734 | MMBtu | $8.07 |
TOTAL ENERGY COSTS | $232,294 | |||
RECOMMENDED SAVINGS* | $17,441 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $14,249 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3137 USE POWER DURING OFF-PEAK PERIODS |
Savings: $4,800 Cost: - |
$4,800 | - | - | - | - | - |
$4,800 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $3,349 Cost: $200 |
$3,349 | 33,705 | - | - | - | - |
$3,349 33,705 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $2,634 Cost: $5,995 |
$(-818) | (-9,965) | $3,452 | 464 | - | - |
$(-818) (-9,965) kWh |
$3,452 464 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.8123 PAY UTILITY BILLS ON TIME |
Savings: $1,820 Cost: - |
- | - | - | - | $1,820 | - |
- - kWh |
- - MMBtu |
$1,820 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,369 Cost: $2,464 |
$1,369 | 10,551 | - | - | - | - |
$1,369 10,551 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7314 REDUCE VENTILATION AIR |
Savings: $1,190 Cost: $3,320 |
- | - | $1,190 | 160 | - | - |
- - kWh |
$1,190 160 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $753 Cost: - |
$753 | 10,844 | - | - | - | - |
$753 10,844 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $612 Cost: $330 |
$612 | 6,155 | - | - | - | - |
$612 6,155 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $558 Cost: $127 |
$558 | 4,689 | - | - | - | - |
$558 4,689 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $356 Cost: $570 |
$356 | 2,931 | - | - | - | - |
$356 2,931 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $17,441 Cost: $13,006 |
$10,979 | 58,910 | $4,642 | 624 | $1,820 | - | $10,979 58,910 kWh |
$4,642 624 MMBtu |
$1,820 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $14,249 Cost: $6,884 |
$11,239 | 64,186 | $1,190 | 160 | $1,820 | - | $11,239 64,186 kWh |
$1,190 160 MMBtu |
$1,820 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |