IAC Assessment: MA0471
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0471
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 2000
Principal Product Lobster storage, packaging and shipping
NAICS n/a
SIC 2092 - Fresh Or Frozen Prepared Fish
Sales $50,000,000-$100,000,000
# of Employees 90
Plant Area (Sq.Ft.) 49,173
Annual Production 1,000,000 Pounds
Production Hrs. Annual 4,056
Location (State) MA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $120,837 2,046,307 kWh $0.06
Electricity Demand $23,217 3,896 kW-months/year $5.96
Natural Gas $14,056 1,814 MMBtu $7.75
TOTAL ENERGY COSTS $169,434
RECOMMENDED SAVINGS* $16,478 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $114
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ MMBtu $ $
01: 4.6520 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES Savings:
$7,546
Cost:
$18,500
$2,536 107,855 - - - - $5,010 - $2,536
107,855
kWh
-
-
kW-months/year
-
-
MMBtu
$5,010
-
$
02: 2.2623 MINIMIZE CONDENSER COOLING WATER TEMPERATURE Savings:
$3,105
Cost:
$11,000
$3,105 53,048 - - - - - - $3,105
53,048
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
03: 2.2121 INCREASE AMOUNT OF CONDENSATE RETURNED Savings:
$2,804
Cost:
$7,200
- - - - $2,804 407 - - -
-
kWh
-
-
kW-months/year
$2,804
407
MMBtu
-
-
$
04: 2.2623 MINIMIZE CONDENSER COOLING WATER TEMPERATURE Savings:
$1,548
Cost:
$4,000
$1,355 23,154 $193 33 - - - - $1,355
23,154
kWh
$193
33
kW-months/year
-
-
MMBtu
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,361
Cost:
$19,740
$1,050 17,878 $311 53 - - - - $1,050
17,878
kWh
$311
53
kW-months/year
-
-
MMBtu
-
-
$
06: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$114
Cost:
$120
$114 1,758 - - - - - - $114
1,758
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$16,478
Cost:
$60,560
$8,160 203,693 $504 86 $2,804 407 $5,010 - $8,160
203,693
kWh
$504
86
kW-months/year
$2,804
407
MMBtu
$5,010
-
$
TOTAL IMPLEMENTED Savings:
$114
Cost:
$120
$114 1,758 - - - - - - $114
1,758
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas One-time Revenue or Avoided Cost