IAC Assessment: MA0578
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0578
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 2005
Principal Product Plastic auto parts
NAICS 336390 - Other Motor Vehicle Parts Manufacturing
SIC 3714 - Motor Vehicle Parts And Accessories
Sales $10,000,000-$50,000,000
# of Employees 181
Plant Area (Sq.Ft.) 345,000
Annual Production 1,165,000 Pieces
Production Hrs. Annual 3,624
Location (State) NH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,280,846 15,519,170 kWh $0.08
Electricity Demand $349,483 46,645 kW-months/year $7.49
Electricity Fees $55,829 - $ -
LPG $896,300 98,726 MMBtu $9.08
TOTAL ENERGY COSTS $2,582,458
RECOMMENDED SAVINGS* $197,823 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $129,142
#|Description Savings
Cost
Status Electricity Usage Electricity Demand LPG Electricity Usage Electricity Demand LPG
$ kWh $ kW-months/year $ MMBtu
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$86,353
Cost:
$20,000
- - $86,353 9,972 - - -
-
kWh
$86,353
9,972
kW-months/year
-
-
MMBtu
02: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$13,684
Cost:
$4,800
$1,043 12,480 - - $12,641 1,107 $1,043
12,480
kWh
-
-
kW-months/year
$12,641
1,107
MMBtu
03: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING Savings:
$4,767
Cost:
$25,000
$4,767 58,273 - - - - $4,767
58,273
kWh
-
-
kW-months/year
-
-
MMBtu
04: 2.2511 INSULATE BARE EQUIPMENT Savings:
$318
Cost:
$327
$401 4,600 - - $(-83) (-9) $401
4,600
kWh
-
-
kW-months/year
$(-83)
(-9)
MMBtu
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,718
Cost:
$5,475
$1,307 15,663 $411 57 - - $1,307
15,663
kWh
$411
57
kW-months/year
-
-
MMBtu
06: 2.1116 IMPROVE COMBUSTION CONTROL CAPABILITY Savings:
$36,304
Cost:
$600
- - - - $36,304 3,179 -
-
kWh
-
-
kW-months/year
$36,304
3,179
MMBtu
07: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$54,679
Cost:
$800
- - - - $54,679 4,788 -
-
kWh
-
-
kW-months/year
$54,679
4,788
MMBtu
TOTAL RECOMMENDED Savings:
$197,823
Cost:
$57,002
$7,518 91,016 $86,764 10,029 $103,541 9,065 $7,518
91,016
kWh
$86,764
10,029
kW-months/year
$103,541
9,065
MMBtu
TOTAL IMPLEMENTED Savings:
$129,142
Cost:
$51,075
$6,074 73,936 $86,764 10,029 $36,304 3,179 $6,074
73,936
kWh
$86,764
10,029
kW-months/year
$36,304
3,179
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand LPG Electricity Usage Electricity Demand LPG