IAC Assessment: MA0722
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0722
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 2014
Principal Product Drinking water
NAICS 221310 - Water Supply and Irrigation Systems
SIC 4941 - Water Supply
Sales $10,000,000-$50,000,000
# of Employees 6
Plant Area (Sq.Ft.) 74,000
Annual Production 5,456,000 Thousand Gallons
Production Hrs. Annual 8,760
Location (State) CT
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $237,081 3,497,760 kWh $0.07
Electricity Demand $93,194 6,101 kW-months/year $15.28
Electricity Fees $949 - $ -
Fuel Oil #2 $106,420 3,787 MMBtu $28.10
TOTAL ENERGY COSTS $437,644
RECOMMENDED SAVINGS* $35,564 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $12,296
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Fuel Oil #2 Administrative Changes Electricity Usage Electricity Demand Fuel Oil #2 Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.3137 USE POWER DURING OFF-PEAK PERIODS Savings:
$11,298
Cost:
$500
- - $10,616 695 - - $682 - -
-
kWh
$10,616
695
kW-months/year
-
-
MMBtu
$682
-
$
02: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY Savings:
$10,940
Cost:
$1,500
$10,940 161,357 - - - - - - $10,940
161,357
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
03: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA Savings:
$3,147
Cost:
$9,900
- - - - $3,147 112 - - -
-
kWh
-
-
kW-months/year
$3,147
112
MMBtu
-
-
$
04: 2.7314 REDUCE VENTILATION AIR Savings:
$2,443
Cost:
$3,000
$55 816 - - $2,388 85 - - $55
816
kWh
-
-
kW-months/year
$2,388
85
MMBtu
-
-
$
05: 2.7312 MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE Savings:
$1,818
Cost:
$2,750
$160 2,369 - - $1,658 59 - - $160
2,369
kWh
-
-
kW-months/year
$1,658
59
MMBtu
-
-
$
06: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$1,742
Cost:
$1,450
- - - - $1,742 62 - - -
-
kWh
-
-
kW-months/year
$1,742
62
MMBtu
-
-
$
07: 2.7314 REDUCE VENTILATION AIR Savings:
$1,630
Cost:
$3,750
- - - - $1,630 58 - - -
-
kWh
-
-
kW-months/year
$1,630
58
MMBtu
-
-
$
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$998
Cost:
$200
$998 14,717 - - - - - - $998
14,717
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
09: 2.8123 PAY UTILITY BILLS ON TIME Savings:
$949
Cost:
$500
- - - - - - $949 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$949
-
$
10: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$599
Cost:
$1,600
$599 8,830 - - - - - - $599
8,830
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$35,564
Cost:
$25,150
$12,752 188,089 $10,616 695 $10,565 376 $1,631 - $12,752
188,089
kWh
$10,616
695
kW-months/year
$10,565
376
MMBtu
$1,631
-
$
TOTAL IMPLEMENTED Savings:
$12,296
Cost:
$700
$998 14,717 $10,616 695 - - $682 - $998
14,717
kWh
$10,616
695
kW-months/year
-
-
MMBtu
$682
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Fuel Oil #2 Administrative Changes Electricity Usage Electricity Demand Fuel Oil #2 Administrative Changes