Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2014 |
Principal Product | Drinking water |
NAICS | 221310 - Water Supply and Irrigation Systems |
SIC | 4941 - Water Supply |
Sales | $10,000,000-$50,000,000 |
# of Employees | 6 |
Plant Area (Sq.Ft.) | 74,000 |
Annual Production | 5,456,000 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | CT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $237,081 | 3,497,760 | kWh | $0.07 |
Electricity Demand | $93,194 | 6,101 | kW-months/year | $15.28 |
Electricity Fees | $949 | - | $ | - |
Fuel Oil #2 | $106,420 | 3,787 | MMBtu | $28.10 |
TOTAL ENERGY COSTS | $437,644 | |||
RECOMMENDED SAVINGS* | $35,564 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $12,296 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Fuel Oil #2 | Administrative Changes | Electricity Usage | Electricity Demand | Fuel Oil #2 | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3137 USE POWER DURING OFF-PEAK PERIODS |
Savings: $11,298 Cost: $500 |
- | - | $10,616 | 695 | - | - | $682 | - |
- - kWh |
$10,616 695 kW-months/year |
- - MMBtu |
$682 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY |
Savings: $10,940 Cost: $1,500 |
$10,940 | 161,357 | - | - | - | - | - | - |
$10,940 161,357 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $3,147 Cost: $9,900 |
- | - | - | - | $3,147 | 112 | - | - |
- - kWh |
- - kW-months/year |
$3,147 112 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7314 REDUCE VENTILATION AIR |
Savings: $2,443 Cost: $3,000 |
$55 | 816 | - | - | $2,388 | 85 | - | - |
$55 816 kWh |
- - kW-months/year |
$2,388 85 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7312 MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE |
Savings: $1,818 Cost: $2,750 |
$160 | 2,369 | - | - | $1,658 | 59 | - | - |
$160 2,369 kWh |
- - kW-months/year |
$1,658 59 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $1,742 Cost: $1,450 |
- | - | - | - | $1,742 | 62 | - | - |
- - kWh |
- - kW-months/year |
$1,742 62 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7314 REDUCE VENTILATION AIR |
Savings: $1,630 Cost: $3,750 |
- | - | - | - | $1,630 | 58 | - | - |
- - kWh |
- - kW-months/year |
$1,630 58 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $998 Cost: $200 |
$998 | 14,717 | - | - | - | - | - | - |
$998 14,717 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.8123 PAY UTILITY BILLS ON TIME |
Savings: $949 Cost: $500 |
- | - | - | - | - | - | $949 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$949 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $599 Cost: $1,600 |
$599 | 8,830 | - | - | - | - | - | - |
$599 8,830 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $35,564 Cost: $25,150 |
$12,752 | 188,089 | $10,616 | 695 | $10,565 | 376 | $1,631 | - | $12,752 188,089 kWh |
$10,616 695 kW-months/year |
$10,565 376 MMBtu |
$1,631 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $12,296 Cost: $700 |
$998 | 14,717 | $10,616 | 695 | - | - | $682 | - | $998 14,717 kWh |
$10,616 695 kW-months/year |
- - MMBtu |
$682 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Fuel Oil #2 | Administrative Changes | Electricity Usage | Electricity Demand | Fuel Oil #2 | Administrative Changes |