IAC Assessment: ME0183
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: ME0183
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Maine
Assessment Year 1996
Principal Product 2'x4'studs
NAICS n/a
SIC 2421 - Sawmills And Planing Mills, General
Sales $10,000,000-$50,000,000
# of Employees 125
Plant Area (Sq.Ft.) 44,000
Annual Production 81,000,000 Thousand Feet
Production Hrs. Annual 4,500
Location (State) ME
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $785,102 11,031,946 kWh $0.07
Electricity Demand $183,369 26,528 kW-months/year $6.91
Electricity Fees $302 - $ -
LPG $6,477 2,997 MMBtu $2.16
Fuel Oil #2 $27,853 7,000 MMBtu $3.98
TOTAL ENERGY COSTS $1,003,103
RECOMMENDED SAVINGS* $82,208 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $64,208
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Fuel Oil #2 Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Fuel Oil #2 Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$23,160
Cost:
$1,200
$23,160 330,891 - - - - - - - - $23,160
330,891
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
02: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES Savings:
$18,000
Cost:
$26,280
- - - - - - - - $18,000 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
$18,000
-
$
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$8,553
Cost:
$10,500
$8,553 122,216 - - - - - - - - $8,553
122,216
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
04: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$8,809
Cost:
-
$8,809 125,733 - - - - - - - - $8,809
125,733
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,901
Cost:
$13,040
$4,893 70,047 $1,008 146 - - - - - - $4,893
70,047
kWh
$1,008
146
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
06: 2.4325 UPGRADE CONVEYORS Savings:
$5,339
Cost:
$6,100
$4,641 66,237 $698 199 - - - - - - $4,641
66,237
kWh
$698
199
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
07: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$5,206
Cost:
$6,000
$3,732 53,341 $2,379 344 $(-905) (-227) - - - - $3,732
53,341
kWh
$2,379
344
kW-months/year
$(-905)
(-227)
MMBtu
-
-
$
-
-
$
08: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$3,000
Cost:
$9,500
- - - - - - $3,000 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$3,000
-
$
-
-
$
09: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$3,133
Cost:
-
$3,133 44,842 - - - - - - - - $3,133
44,842
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
10: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$1,107
Cost:
-
- - - - - - $1,107 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,107
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$82,208
Cost:
$72,620
$56,921 813,307 $4,085 689 $(-905) (-227) $4,107 - $18,000 - $56,921
813,307
kWh
$4,085
689
kW-months/year
$(-905)
(-227)
MMBtu
$4,107
-
$
$18,000
-
$
TOTAL IMPLEMENTED Savings:
$64,208
Cost:
$46,340
$56,921 813,307 $4,085 689 $(-905) (-227) $4,107 - - - $56,921
813,307
kWh
$4,085
689
kW-months/year
$(-905)
(-227)
MMBtu
$4,107
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Fuel Oil #2 Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Fuel Oil #2 Administrative Changes Ancillary Material Cost