Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Maine |
---|---|
Assessment Year | 1997 |
Principal Product | cardboard containers |
NAICS | n/a |
SIC | 2653 - Corrugated And Solid Fiber Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 165,000 |
Annual Production | 650,000,000 Thousand Feet |
Production Hrs. Annual | 6,860 |
Location (State) | ME |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $201,859 | 3,558,910 | kWh | $0.06 |
Electricity Demand | $89,044 | 11,594 | kW-months/year | $7.68 |
Electricity Fees | $121 | - | $ | - |
Natural Gas | $116,891 | 30,772 | MMBtu | $3.80 |
LPG | $12,832 | 1,538 | MMBtu | $8.34 |
Fuel Oil #2 | $15,946 | 3,795 | MMBtu | $4.20 |
TOTAL ENERGY COSTS | $453,711 | |||
RECOMMENDED SAVINGS* | $99,430 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $62,444 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Fuel Oil #2 | Water Disposal | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Fuel Oil #2 | Water Disposal | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | $ | $ | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $25,155 Cost: $8,223 |
$20,160 | 335,873 | $11,059 | 1,440 | $(-3,389) | (-891) | $(-2,675) | (-637) | - | - | - | - | - | - | - | - | - | - |
$20,160 335,873 kWh |
$11,059 1,440 kW-months/year |
$(-3,389) (-891) MMBtu |
$(-2,675) (-637) MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $17,912 Cost: $32,046 |
$14,551 | 242,380 | $3,361 | 437 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$14,551 242,380 kWh |
$3,361 437 kW-months/year |
- - MMBtu |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $7,434 Cost: $1,980 |
$7,434 | 123,974 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$7,434 123,974 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $5,853 Cost: $925 |
$5,853 | 97,597 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$5,853 97,597 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $2,583 Cost: $486 |
$2,583 | 43,083 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$2,583 43,083 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,024 Cost: - |
$2,024 | 33,705 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$2,024 33,705 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $930 Cost: $30 |
$930 | 15,533 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$930 15,533 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7291 RESCHEDULE AND REARRANGE MULTIPLE-SOURCE HEATING SYSTEMS |
Savings: $662 Cost: - |
$524 | 8,792 | $138 | 18 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$524 8,792 kWh |
$138 18 kW-months/year |
- - MMBtu |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $432 Cost: $91 |
$432 | 26,671 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$432 26,671 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.1193 CONVERT FROM BATCH OPERATION TO CONTINUOUS PROCESSING |
Savings: $36,223 Cost: $200,000 |
- | - | - | - | - | - | - | - | - | - | $443 | 18,200 | $28,500 | - | $7,280 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - Tgal |
$443 18,200 lb |
$28,500 - $ |
$7,280 - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.4151 MINIMIZE WATER USAGE |
Savings: $222 Cost: $110 |
- | - | - | - | - | - | - | - | $185 | 26,000 | - | - | - | - | - | - | $37 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
$185 26,000 Tgal |
- - lb |
- - $ |
- - $ |
$37 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $99,430 Cost: $243,891 |
$54,491 | 927,608 | $14,558 | 1,895 | $(-3,389) | (-891) | $(-2,675) | (-637) | $185 | 26,000 | $443 | 18,200 | $28,500 | - | $7,280 | - | $37 | - | $54,491 927,608 kWh |
$14,558 1,895 kW-months/year |
$(-3,389) (-891) MMBtu |
$(-2,675) (-637) MMBtu |
$185 26,000 Tgal |
$443 18,200 lb |
$28,500 - $ |
$7,280 - $ |
$37 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $62,444 Cost: $233,062 |
$22,860 | 400,353 | $3,361 | 437 | - | - | - | - | - | - | $443 | 18,200 | $28,500 | - | $7,280 | - | - | - | $22,860 400,353 kWh |
$3,361 437 kW-months/year |
- - MMBtu |
- - MMBtu |
- - Tgal |
$443 18,200 lb |
$28,500 - $ |
$7,280 - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | $ | $ | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Fuel Oil #2 | Water Disposal | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Fuel Oil #2 | Water Disposal | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | Water Consumption |