Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Maine |
---|---|
Assessment Year | 1997 |
Principal Product | Glued Wood Dimensions |
NAICS | n/a |
SIC | 2426 - Hardwood Dimension & Flooring Mills |
Sales | $5,000,000-$10,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 50,000 |
Annual Production | 9,000,000 Thousand Feet |
Production Hrs. Annual | 4,100 |
Location (State) | ME |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $175,918 | 2,940,797 | kWh | $0.06 |
Electricity Demand | $70,387 | 10,726 | kW-months/year | $6.56 |
Electricity Fees | $6,453 | - | $ | - |
LPG | $2,678 | 179 | MMBtu | $14.96 |
Fuel Oil #1 | $1,509 | 175 | MMBtu | $8.62 |
Fuel Oil #2 | $34,620 | 4,162 | MMBtu | $8.32 |
Other Energy | $5,811 | 585 | MMBtu | $9.93 |
TOTAL ENERGY COSTS | $297,376 | |||
RECOMMENDED SAVINGS* | $22,747 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $15,547 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Fuel Oil #2 | Wood | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Fuel Oil #2 | Wood | Solid Waste (non-haz) | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.231 PURCHASE EQUIPMENT INSTEAD OF LEASING |
Savings: $7,200 Cost: $27,375 |
- | - | - | - | - | - | - | - | - | - | $7,200 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
$7,200 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,389 Cost: $8,204 |
$4,995 | 53,634 | $394 | 60 | - | - | - | - | - | - | - | - |
$4,995 53,634 kWh |
$394 60 kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $3,895 Cost: $13,215 |
$3,214 | 53,341 | $681 | 103 | - | - | - | - | - | - | - | - |
$3,214 53,341 kWh |
$681 103 kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,941 Cost: $3,276 |
$2,941 | 48,945 | - | - | - | - | - | - | - | - | - | - |
$2,941 48,945 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $1,517 Cost: $3,844 |
$1,492 | 24,912 | $683 | 104 | $(-658) | (-106) | - | - | - | - | - | - |
$1,492 24,912 kWh |
$683 104 kW-months/year |
$(-658) (-106) MMBtu |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $597 Cost: $603 |
- | - | - | - | - | - | $597 | 354 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$597 354 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $564 Cost: $325 |
$564 | 9,379 | - | - | - | - | - | - | - | - | - | - |
$564 9,379 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $144 Cost: - |
- | - | - | - | - | - | - | - | - | - | $144 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
$144 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $500 Cost: - |
- | - | - | - | - | - | - | - | $500 | 40,000 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
$500 40,000 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,747 Cost: $56,842 |
$13,206 | 190,211 | $1,758 | 267 | $(-658) | (-106) | $597 | 354 | $500 | 40,000 | $7,344 | - | $13,206 190,211 kWh |
$1,758 267 kW-months/year |
$(-658) (-106) MMBtu |
$597 354 MMBtu |
$500 40,000 lb |
$7,344 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $15,547 Cost: $29,467 |
$13,206 | 190,211 | $1,758 | 267 | $(-658) | (-106) | $597 | 354 | $500 | 40,000 | $144 | - | $13,206 190,211 kWh |
$1,758 267 kW-months/year |
$(-658) (-106) MMBtu |
$597 354 MMBtu |
$500 40,000 lb |
$144 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Fuel Oil #2 | Wood | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Fuel Oil #2 | Wood | Solid Waste (non-haz) | Administrative Changes |