Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Maine |
---|---|
Assessment Year | 1999 |
Principal Product | Impellers |
NAICS | n/a |
SIC | 3511 - Turbines And Turbine Generator Sets |
Sales | $5,000,000-$10,000,000 |
# of Employees | 52 |
Plant Area (Sq.Ft.) | 25,600 |
Annual Production | 1,250 Pieces |
Production Hrs. Annual | 4,750 |
Location (State) | NH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $50,997 | 538,980 | kWh | $0.09 |
Electricity Demand | $150,858 | 1,715 | kW-months/year | $87.96 |
Electricity Fees | $1,129 | - | $ | - |
Natural Gas | $4,725 | 675 | MMBtu | $7.00 |
TOTAL ENERGY COSTS | $224,859 | |||
RECOMMENDED SAVINGS* | $30,253 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $26,828 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (haz) | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (haz) | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING |
Savings: $7,332 Cost: $5,655 |
$7,332 | 81,477 | - | - | - | - | - | - | - | - | - | - | - | - |
$7,332 81,477 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,027 Cost: $9,340 |
$1,605 | 17,878 | $422 | 48 | - | - | - | - | - | - | - | - | - | - |
$1,605 17,878 kWh |
$422 48 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $896 Cost: - |
$896 | 9,965 | - | - | - | - | - | - | - | - | - | - | - | - |
$896 9,965 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.8112 COMBINE UTILITY METERS |
Savings: $456 Cost: $230 |
- | - | - | - | - | - | - | - | - | - | $456 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$456 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.8112 COMBINE UTILITY METERS |
Savings: $450 Cost: $720 |
- | - | - | - | - | - | - | - | - | - | $450 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$450 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $370 Cost: $1,000 |
$370 | 4,103 | - | - | - | - | - | - | - | - | - | - | - | - |
$370 4,103 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $365 Cost: $400 |
- | - | - | - | $365 | 49 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$365 49 MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $285 Cost: $215 |
$285 | 3,224 | - | - | - | - | - | - | - | - | - | - | - | - |
$285 3,224 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $14,100 Cost: $955,000 |
- | - | - | - | - | - | $14,100 | 1,024 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$14,100 1,024 gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $2,290 Cost: $2,460 |
- | - | - | - | - | - | - | - | - | - | $2,290 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$2,290 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.8134 USE WATER-BASED CUTTING FLUIDS TO ELIMINATE NEED FOR SOLVENT CLEANING |
Savings: $917 Cost: - |
- | - | - | - | - | - | $917 | 183 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$917 183 gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 3.7223 INSTALL SHROUDING ON MACHINES TO PREVENT SPLASHING |
Savings: $473 Cost: $5,240 |
- | - | - | - | - | - | $473 | 37 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$473 37 gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $292 Cost: - |
- | - | - | - | - | - | - | - | $80 | 2,667 | - | - | $212 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$80 2,667 lb |
- - $ |
$212 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $30,253 Cost: $980,260 |
$10,488 | 116,647 | $422 | 48 | $365 | 49 | $15,490 | 1,244 | $80 | 2,667 | $3,196 | - | $212 | - | $10,488 116,647 kWh |
$422 48 kW-months/year |
$365 49 MMBtu |
$15,490 1,244 gal |
$80 2,667 lb |
$3,196 - $ |
$212 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $26,828 Cost: $971,560 |
$10,118 | 112,544 | $422 | 48 | $365 | 49 | $15,017 | 1,207 | - | - | $906 | - | - | - | $10,118 112,544 kWh |
$422 48 kW-months/year |
$365 49 MMBtu |
$15,017 1,207 gal |
- - lb |
$906 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (haz) | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (haz) | Administrative Changes | Ancillary Material Cost |