IAC logo
IAC Assessment: MI0012
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MI0012
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Miami
Assessment Year 2001
Principal Product Elevator cars and entrances
NAICS n/a
SIC 3534 - Elevators And Moving Stairways
Sales $10,000,000-$50,000,000
# of Employees 110
Plant Area (Sq.Ft.) 70,000
Annual Production 0 Units
Production Hrs. Annual 2,470
Location (State) FL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $27,709 581,820 kWh $0.05
Electricity Demand $26,950 3,180 kW-months/year $8.47
TOTAL ENERGY COSTS $54,659
RECOMMENDED SAVINGS* $74,399 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $74,399
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Primary Product Electricity Usage Electricity Demand Primary Product
$ kWh $ kW-months/year $ $
01: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$656
Cost:
$260
$656 12,370 - - - - $656
12,370
kWh
-
-
kW-months/year
-
-
$
02: 4.712 UTILIZE JOB COSTING SOFTWARE Savings:
$58,500
Cost:
$12,000
- - - - $58,500 - -
-
kWh
-
-
kW-months/year
$58,500
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,550
Cost:
$306
$3,550 71,000 - - - - $3,550
71,000
kWh
-
-
kW-months/year
-
-
$
04: 4.512 CONDENSE OPERATION INTO ONE BUILDING Savings:
$5,315
Cost:
$2,040
- - - - $5,315 - -
-
kWh
-
-
kW-months/year
$5,315
-
$
05: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP Savings:
$4,188
Cost:
$5,000
$4,188 46,493 - - - - $4,188
46,493
kWh
-
-
kW-months/year
-
-
$
06: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS Savings:
$2,190
Cost:
$29
- - $2,190 260 - - -
-
kWh
$2,190
260
kW-months/year
-
-
$
TOTAL RECOMMENDED Savings:
$74,399
Cost:
$19,635
$8,394 129,863 $2,190 260 $63,815 - $8,394
129,863
kWh
$2,190
260
kW-months/year
$63,815
-
$
TOTAL IMPLEMENTED Savings:
$74,399
Cost:
$19,635
$8,394 129,863 $2,190 260 $63,815 - $8,394
129,863
kWh
$2,190
260
kW-months/year
$63,815
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Primary Product Electricity Usage Electricity Demand Primary Product