Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2002 |
Principal Product | Stone cutting and mining |
NAICS | n/a |
SIC | 3281 - Cut Stone And Stone Products |
Sales | $50,000,000-$100,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 40,000 |
Annual Production | 12,000,000 Pieces |
Production Hrs. Annual | 3,432 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $390,524 | 7,056,080 | kWh | $0.06 |
Electricity Demand | $139,713 | 50,410 | kW-months/year | $2.77 |
TOTAL ENERGY COSTS | $530,237 | |||
RECOMMENDED SAVINGS* | $257,590 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $57,213 |
#|Description |
Savings Cost |
Status | Electricity Demand | Administrative Changes | Primary Product | Electricity Demand | Administrative Changes | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8211 CONSOLIDATE FREIGHT SHIPMENTS AND/OR DELIVERIES |
Savings: $131,820 Cost: $30 |
- | - | $131,820 | - | - | - |
- - kW-months/year |
$131,820 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.3121 USE SCREENING, MAGNETIC SEPARATION TO REMOVE CONTAMINANTS |
Savings: $38,400 Cost: $10,372 |
- | - | - | - | $38,400 | - |
- - kW-months/year |
- - $ |
$38,400 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4112 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS |
Savings: $30,176 Cost: $37,105 |
$30,176 | 10,894 | - | - | - | - |
$30,176 10,894 kW-months/year |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $21,898 Cost: $1,820 |
$21,898 | 7,906 | - | - | - | - |
$21,898 7,906 kW-months/year |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $18,813 Cost: $23,000 |
- | - | - | - | $18,813 | - |
- - kW-months/year |
- - $ |
$18,813 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $16,483 Cost: $1,137 |
$16,483 | 230,455 | - | - | - | - |
$16,483 230,455 kW-months/year |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $257,590 Cost: $73,464 |
$68,557 | 249,255 | $131,820 | - | $57,213 | - | $68,557 249,255 kW-months/year |
$131,820 - $ |
$57,213 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $57,213 Cost: $33,372 |
- | - | - | - | $57,213 | - | - - kW-months/year |
- - $ |
$57,213 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Demand | Administrative Changes | Primary Product | Electricity Demand | Administrative Changes | Primary Product |