Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2020 |
Principal Product | pet bottles, jars |
NAICS | 326160 - Plastics Bottle Manufacturing |
SIC | 3085 - Plastics Bottles |
Sales | $10,000,000-$50,000,000 |
# of Employees | 72 |
Plant Area (Sq.Ft.) | 45,000 |
Annual Production | 70,000,000 Pieces |
Production Hrs. Annual | 7,344 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $151,367 | 3,777,861 | kWh | $0.04 |
Electricity Demand | $117,722 | 8,745 | kW-months/year | $13.46 |
Electricity Fees | $37,460 | - | $ | - |
TOTAL ENERGY COSTS | $324,492 | |||
RECOMMENDED SAVINGS* | $34,220 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Electricity Usage | Electricity Demand | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $9,975 Cost: $1,980 |
$3,190 | 79,762 | $6,785 | 504 | - | - |
$3,190 79,762 kWh |
$6,785 504 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $7,215 Cost: $2,100 |
$4,415 | 110,384 | $2,800 | 208 | - | - |
$4,415 110,384 kWh |
$2,800 208 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) |
Savings: $4,058 Cost: $1,306 |
- | - | - | - | $4,058 | 481 |
- - kWh |
- - kW-months/year |
$4,058 481 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7252 UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM |
Savings: $3,560 Cost: $17,760 |
$2,295 | 57,370 | $1,265 | 94 | - | - |
$2,295 57,370 kWh |
$1,265 94 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $2,125 Cost: $2,048 |
$792 | 19,809 | $1,333 | 99 | - | - |
$792 19,809 kWh |
$1,333 99 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7229 AIR CONDITION ONLY SPACE NECESSARY |
Savings: $1,976 Cost: $4,415 |
$1,276 | 31,892 | $700 | 52 | - | - |
$1,276 31,892 kWh |
$700 52 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,479 Cost: $1,875 |
$954 | 23,854 | $525 | 39 | - | - |
$954 23,854 kWh |
$525 39 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,242 Cost: $1,042 |
$1,242 | 31,049 | - | - | - | - |
$1,242 31,049 kWh |
- - kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $1,158 Cost: $1,827 |
- | - | $1,158 | 86 | - | - |
- - kWh |
$1,158 86 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7228 AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM |
Savings: $744 Cost: $965 |
$488 | 12,210 | $256 | 19 | - | - |
$488 12,210 kWh |
$256 19 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $688 Cost: $682 |
$271 | 6,783 | $417 | 31 | - | - |
$271 6,783 kWh |
$417 31 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $34,220 Cost: $36,000 |
$14,923 | 373,113 | $15,239 | 1,132 | $4,058 | 481 | $14,923 373,113 kWh |
$15,239 1,132 kW-months/year |
$4,058 481 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Electricity Usage | Electricity Demand | Water Disposal |