Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2023 |
Principal Product | Medical Devices |
NAICS | 339112 - Surgical and Medical Instrument Manufacturing |
SIC | 3841 - Surgical And Medical Instruments |
Sales | $10,000,000-$50,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 72,000 |
Annual Production | 1,000,000 Pieces |
Production Hrs. Annual | 8,568 |
Location (State) | PR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,428,992 | 5,567,760 | kWh | $0.26 |
Electricity Demand | $82,200 | 10,046 | kW-months/year | $8.18 |
Electricity Fees | $5,203 | - | $ | - |
TOTAL ENERGY COSTS | $1,516,395 | |||
RECOMMENDED SAVINGS* | $48,336 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $26,925 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Electricity Usage | Electricity Demand | Electricity Fees | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $18,053 Cost: $1,060 |
$16,491 | 64,167 | $1,562 | 191 | - | - |
$16,491 64,167 kWh |
$1,562 191 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $14,947 Cost: $240 |
$14,309 | 55,678 | $638 | 78 | - | - |
$14,309 55,678 kWh |
$638 78 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $7,069 Cost: $4,697 |
$6,753 | 26,276 | $316 | 39 | - | - |
$6,753 26,276 kWh |
$316 39 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $2,790 Cost: $4,860 |
$2,671 | 10,393 | $119 | 15 | - | - |
$2,671 10,393 kWh |
$119 15 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $1,869 Cost: $100 |
- | - | - | - | $1,869 | - |
- - kWh |
- - kW-months/year |
$1,869 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $1,805 Cost: $2,630 |
$1,159 | 4,509 | $646 | 79 | - | - |
$1,159 4,509 kWh |
$646 79 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,803 Cost: $791 |
$1,726 | 6,717 | $77 | 9 | - | - |
$1,726 6,717 kWh |
$77 9 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $48,336 Cost: $14,378 |
$43,109 | 167,740 | $3,358 | 411 | $1,869 | - | $43,109 167,740 kWh |
$3,358 411 kW-months/year |
$1,869 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $26,925 Cost: $6,548 |
$24,970 | 97,160 | $1,955 | 239 | - | - | $24,970 97,160 kWh |
$1,955 239 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Electricity Usage | Electricity Demand | Electricity Fees |