Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri, Rolla |
---|---|
Assessment Year | 1995 |
Principal Product | sealant and closed-cell rubber |
NAICS | n/a |
SIC | 3069 - Fabricated Rubber Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 180,000 |
Annual Production | 10,100,000 Pounds |
Production Hrs. Annual | 6,120 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $444,124 | 7,194,021 | kWh | $0.06 |
Natural Gas | $183,249 | 43,180 | MMBtu | $4.24 |
TOTAL ENERGY COSTS | $724,371 | |||
RECOMMENDED SAVINGS* | $106,328 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,041 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Water Disposal | Administrative Changes | Electricity Usage | Natural Gas | Water Disposal | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $2,220 Cost: $995 |
- | - | $2,220 | 524 | - | - | - | - |
- - kWh |
$2,220 524 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER |
Savings: $26,406 Cost: $300 |
- | - | - | - | - | - | $26,406 | - |
- - kWh |
- - MMBtu |
- - Tgal |
$26,406 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $540 Cost: $365 |
$540 | 8,499 | - | - | - | - | - | - |
$540 8,499 kWh |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $2,849 Cost: $7,562 |
$2,849 | 46,600 | - | - | - | - | - | - |
$2,849 46,600 kWh |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,743 Cost: $1,063 |
$2,743 | 45,135 | - | - | - | - | - | - |
$2,743 45,135 kWh |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,648 Cost: $3,010 |
$5,648 | 92,907 | - | - | - | - | - | - |
$5,648 92,907 kWh |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $193 Cost: $276 |
$193 | 3,224 | - | - | - | - | - | - |
$193 3,224 kWh |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $4,192 Cost: $702 |
$4,192 | 65,651 | - | - | - | - | - | - |
$4,192 65,651 kWh |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.4114 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER |
Savings: $61,537 Cost: $5,000 |
$(-256) | (-4,396) | - | - | $61,793 | 24,424 | - | - |
$(-256) (-4,396) kWh |
- - MMBtu |
$61,793 24,424 Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $106,328 Cost: $19,273 |
$15,909 | 257,620 | $2,220 | 524 | $61,793 | 24,424 | $26,406 | - | $15,909 257,620 kWh |
$2,220 524 MMBtu |
$61,793 24,424 Tgal |
$26,406 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,041 Cost: $8,264 |
$7,041 | 112,251 | - | - | - | - | - | - | $7,041 112,251 kWh |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Water Disposal | Administrative Changes | Electricity Usage | Natural Gas | Water Disposal | Administrative Changes |