Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri, Rolla |
---|---|
Assessment Year | 1997 |
Principal Product | Curtains |
NAICS | n/a |
SIC | 2391 - Curtains And Draperies |
Sales | $5,000,000-$10,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 50,000 |
Annual Production | 1,300,000 Pieces |
Production Hrs. Annual | 3,380 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $40,262 | 682,884 | kWh | $0.06 |
Electricity Fees | $2,506 | - | $ | - |
Natural Gas | $14,585 | 1,742 | MMBtu | $8.37 |
TOTAL ENERGY COSTS | $65,153 | |||
RECOMMENDED SAVINGS* | $48,065 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $15,243 |
#|Description |
Savings Cost |
Status | Electricity Usage | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Solid Waste (non-haz) | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.711 INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM |
Savings: $17,085 Cost: $25,000 |
- | - | - | - | $17,085 | - |
- - kWh |
- - lb |
$17,085 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.432 CROSS-TRAIN PERSONNEL TO AVOID LOST TIME |
Savings: $6,120 Cost: $15,000 |
- | - | - | - | $6,120 | - |
- - kWh |
- - lb |
$6,120 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.514 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS |
Savings: $5,000 Cost: $12,500 |
- | - | - | - | $5,000 | - |
- - kWh |
- - lb |
$5,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,571 Cost: $7,904 |
$3,571 | 57,151 | - | - | - | - |
$3,571 57,151 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,415 Cost: $2,023 |
$3,415 | 54,513 | - | - | - | - |
$3,415 54,513 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $209 Cost: $345 |
$209 | 3,224 | - | - | - | - |
$209 3,224 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,125 Cost: $80 |
$3,125 | 49,824 | - | - | - | - |
$3,125 49,824 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $708 Cost: $1,794 |
$708 | 11,430 | - | - | - | - |
$708 11,430 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4321 UPGRADE OBSOLETE EQUIPMENT |
Savings: $7,800 Cost: $3,040 |
- | - | $7,800 | 507 | - | - |
- - kWh |
$7,800 507 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.7196 USE RE-USABLE FILTERS |
Savings: $1,032 Cost: $1,236 |
- | - | $1,032 | 276 | - | - |
- - kWh |
$1,032 276 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $48,065 Cost: $68,922 |
$11,028 | 176,142 | $8,832 | 783 | $28,205 | - | $11,028 176,142 kWh |
$8,832 783 lb |
$28,205 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $15,243 Cost: $31,317 |
$4,123 | 65,943 | - | - | $11,120 | - | $4,123 65,943 kWh |
- - lb |
$11,120 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Solid Waste (non-haz) | Ancillary Material Cost |