IAC logo
IAC Assessment: MO0213
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MO0213
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Missouri, Rolla
Assessment Year 1997
Principal Product Railway Rolling Stock and Parts
NAICS n/a
SIC 3743 - Railroad Equipment
Sales $10,000,000-$50,000,000
# of Employees 110
Plant Area (Sq.Ft.) 165,000
Annual Production 1,225 Pieces
Production Hrs. Annual 5,200
Location (State) MO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $105,526 4,310,375 kWh $0.02
Electricity Demand $61,602 931 kW-months/year $66.17
Electricity Fees $11,609 - $ -
Natural Gas $18,133 3,980 MMBtu $4.56
TOTAL ENERGY COSTS $367,910
RECOMMENDED SAVINGS* $205,951 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $34,944
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Other Liquid (non-haz) Solid Waste (non-haz) Ancillary Material Cost Electricity Usage Electricity Demand Other Liquid (non-haz) Solid Waste (non-haz) Ancillary Material Cost
$ kWh $ kW-months/year $ gal $ lb $ $
01: 4.4320 CROSS-TRAIN PERSONNEL TO AVOID LOST TIME Savings:
$12,142
Cost:
$20,000
- - - - - - - - $12,142 - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
lb
$12,142
-
$
02: 4.5140 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS Savings:
$8,250
Cost:
$10,000
- - - - - - - - $8,250 - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
lb
$8,250
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,811
Cost:
$10,944
$2,494 91,735 $1,317 20 - - - - - - $2,494
91,735
kWh
$1,317
20
kW-months/year
-
-
gal
-
-
lb
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,904
Cost:
$1,046
$1,242 45,721 $662 10 - - - - - - $1,242
45,721
kWh
$662
10
kW-months/year
-
-
gal
-
-
lb
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$142
Cost:
$414
$109 4,103 $33 1 - - - - - - $109
4,103
kWh
$33
1
kW-months/year
-
-
gal
-
-
lb
-
-
$
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,326
Cost:
$3,383
$903 33,118 $423 6 - - - - - - $903
33,118
kWh
$423
6
kW-months/year
-
-
gal
-
-
lb
-
-
$
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$6,372
Cost:
$80
$4,341 159,730 $2,031 31 - - - - - - $4,341
159,730
kWh
$2,031
31
kW-months/year
-
-
gal
-
-
lb
-
-
$
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$964
Cost:
$180
$31 7,327 $933 14 - - - - - - $31
7,327
kWh
$933
14
kW-months/year
-
-
gal
-
-
lb
-
-
$
09: 2.4321 UPGRADE OBSOLETE EQUIPMENT Savings:
$166,090
Cost:
$85,000
- - - - - - $166,090 45,000 - - -
-
kWh
-
-
kW-months/year
-
-
gal
$166,090
45,000
lb
-
-
$
10: 2.4321 UPGRADE OBSOLETE EQUIPMENT Savings:
$4,950
Cost:
$6,000
- - - - $4,950 990 - - - - -
-
kWh
-
-
kW-months/year
$4,950
990
gal
-
-
lb
-
-
$
TOTAL RECOMMENDED Savings:
$205,951
Cost:
$137,047
$9,120 341,734 $5,399 82 $4,950 990 $166,090 45,000 $20,392 - $9,120
341,734
kWh
$5,399
82
kW-months/year
$4,950
990
gal
$166,090
45,000
lb
$20,392
-
$
TOTAL IMPLEMENTED Savings:
$34,944
Cost:
$40,509
$6,486 238,569 $3,116 47 $4,950 990 - - $20,392 - $6,486
238,569
kWh
$3,116
47
kW-months/year
$4,950
990
gal
-
-
lb
$20,392
-
$
Savings
Cost
$ kWh $ kW-months/year $ gal $ lb $ $
Electricity Usage Electricity Demand Other Liquid (non-haz) Solid Waste (non-haz) Ancillary Material Cost Electricity Usage Electricity Demand Other Liquid (non-haz) Solid Waste (non-haz) Ancillary Material Cost