Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri, Rolla |
---|---|
Assessment Year | 1997 |
Principal Product | Railway Rolling Stock and Parts |
NAICS | n/a |
SIC | 3743 - Railroad Equipment |
Sales | $10,000,000-$50,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 165,000 |
Annual Production | 1,225 Pieces |
Production Hrs. Annual | 5,200 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $105,526 | 4,310,375 | kWh | $0.02 |
Electricity Demand | $61,602 | 931 | kW-months/year | $66.17 |
Electricity Fees | $11,609 | - | $ | - |
Natural Gas | $18,133 | 3,980 | MMBtu | $4.56 |
TOTAL ENERGY COSTS | $367,910 | |||
RECOMMENDED SAVINGS* | $205,951 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $34,944 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Solid Waste (non-haz) | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | gal | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.432 CROSS-TRAIN PERSONNEL TO AVOID LOST TIME |
Savings: $12,142 Cost: $20,000 |
- | - | - | - | - | - | - | - | $12,142 | - |
- - kWh |
- - kW-months/year |
- - gal |
- - lb |
$12,142 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.514 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS |
Savings: $8,250 Cost: $10,000 |
- | - | - | - | - | - | - | - | $8,250 | - |
- - kWh |
- - kW-months/year |
- - gal |
- - lb |
$8,250 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,811 Cost: $10,944 |
$2,494 | 91,735 | $1,317 | 20 | - | - | - | - | - | - |
$2,494 91,735 kWh |
$1,317 20 kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,904 Cost: $1,046 |
$1,242 | 45,721 | $662 | 10 | - | - | - | - | - | - |
$1,242 45,721 kWh |
$662 10 kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $142 Cost: $414 |
$109 | 4,103 | $33 | 1 | - | - | - | - | - | - |
$109 4,103 kWh |
$33 1 kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,326 Cost: $3,383 |
$903 | 33,118 | $423 | 6 | - | - | - | - | - | - |
$903 33,118 kWh |
$423 6 kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $6,372 Cost: $80 |
$4,341 | 159,730 | $2,031 | 31 | - | - | - | - | - | - |
$4,341 159,730 kWh |
$2,031 31 kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $964 Cost: $180 |
$31 | 7,327 | $933 | 14 | - | - | - | - | - | - |
$31 7,327 kWh |
$933 14 kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4321 UPGRADE OBSOLETE EQUIPMENT |
Savings: $166,090 Cost: $85,000 |
- | - | - | - | - | - | $166,090 | 45,000 | - | - |
- - kWh |
- - kW-months/year |
- - gal |
$166,090 45,000 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4321 UPGRADE OBSOLETE EQUIPMENT |
Savings: $4,950 Cost: $6,000 |
- | - | - | - | $4,950 | 990 | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,950 990 gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $205,951 Cost: $137,047 |
$9,120 | 341,734 | $5,399 | 82 | $4,950 | 990 | $166,090 | 45,000 | $20,392 | - | $9,120 341,734 kWh |
$5,399 82 kW-months/year |
$4,950 990 gal |
$166,090 45,000 lb |
$20,392 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $34,944 Cost: $40,509 |
$6,486 | 238,569 | $3,116 | 47 | $4,950 | 990 | - | - | $20,392 | - | $6,486 238,569 kWh |
$3,116 47 kW-months/year |
$4,950 990 gal |
- - lb |
$20,392 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | gal | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Solid Waste (non-haz) | Ancillary Material Cost |