IAC logo
IAC Assessment: MO0232
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MO0232
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Missouri, Rolla
Assessment Year 1998
Principal Product Fabricated Rubber Products (Injection Molding)
NAICS n/a
SIC 3069 - Fabricated Rubber Products, Nec
Sales $10,000,000-$50,000,000
# of Employees 226
Plant Area (Sq.Ft.) 196,150
Annual Production 8,516,000 Pounds
Production Hrs. Annual 2,080
Location (State) MO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $314,973 14,483,001 kWh $0.02
Electricity Demand $340,412 2,954 kW-months/year $115.24
Electricity Fees $26,979 - $ -
Natural Gas $65,887 11,096 MMBtu $5.94
LPG $6,391 785 MMBtu $8.14
TOTAL ENERGY COSTS $755,794
RECOMMENDED SAVINGS* $42,359 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $39,938
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Ancillary Material Cost Electricity Usage Electricity Demand Solid Waste (non-haz) Ancillary Material Cost
$ kWh $ kW-months/year $ lb $ $
01: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$12,992
Cost:
$6,071
- - - - - - $12,992 - -
-
kWh
-
-
kW-months/year
-
-
lb
$12,992
-
$
02: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE Savings:
$1,792
Cost:
$3,700
- - - - - - $1,792 - -
-
kWh
-
-
kW-months/year
-
-
lb
$1,792
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,988
Cost:
$3,648
$1,259 53,341 $1,729 15 - - - - $1,259
53,341
kWh
$1,729
15
kW-months/year
-
-
lb
-
-
$
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,604
Cost:
$166
$913 38,687 $691 6 - - - - $913
38,687
kWh
$691
6
kW-months/year
-
-
lb
-
-
$
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$817
Cost:
$80
$471 19,930 $346 3 - - - - $471
19,930
kWh
$346
3
kW-months/year
-
-
lb
-
-
$
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$5,253
Cost:
$1,136
$2,948 124,853 $2,305 20 - - - - $2,948
124,853
kWh
$2,305
20
kW-months/year
-
-
lb
-
-
$
07: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$5,576
Cost:
$9,724
$3,156 133,646 $2,420 21 - - - - $3,156
133,646
kWh
$2,420
21
kW-months/year
-
-
lb
-
-
$
08: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$451
Cost:
-
$221 9,379 $230 2 - - - - $221
9,379
kWh
$230
2
kW-months/year
-
-
lb
-
-
$
09: 3.5218 REUSE / RECYCLE/ SELL RUBBER PRODUCTS Savings:
$10,886
Cost:
-
- - - - $10,886 1,152 - - -
-
kWh
-
-
kW-months/year
$10,886
1,152
lb
-
-
$
TOTAL RECOMMENDED Savings:
$42,359
Cost:
$24,525
$8,968 379,836 $7,721 67 $10,886 1,152 $14,784 - $8,968
379,836
kWh
$7,721
67
kW-months/year
$10,886
1,152
lb
$14,784
-
$
TOTAL IMPLEMENTED Savings:
$39,938
Cost:
$24,279
$7,584 321,219 $6,684 58 $10,886 1,152 $14,784 - $7,584
321,219
kWh
$6,684
58
kW-months/year
$10,886
1,152
lb
$14,784
-
$
Savings
Cost
$ kWh $ kW-months/year $ lb $ $
Electricity Usage Electricity Demand Solid Waste (non-haz) Ancillary Material Cost Electricity Usage Electricity Demand Solid Waste (non-haz) Ancillary Material Cost