Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri, Rolla |
---|---|
Assessment Year | 1998 |
Principal Product | Automobile Glove Box Doors and Instrament Panels |
NAICS | n/a |
SIC | 3714 - Motor Vehicle Parts And Accessories |
Sales | $50,000,000-$100,000,000 |
# of Employees | 450 |
Plant Area (Sq.Ft.) | 82,035 |
Annual Production | 554,749 Pieces |
Production Hrs. Annual | 4,160 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $400,327 | 13,610,199 | kWh | $0.03 |
Electricity Demand | $333,096 | 2,383 | kW-months/year | $139.78 |
Electricity Fees | $111,119 | - | $ | - |
Natural Gas | $303,651 | 68,449 | MMBtu | $4.44 |
TOTAL ENERGY COSTS | $1,254,761 | |||
RECOMMENDED SAVINGS* | $1,003,555 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $86,344 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $2,054 Cost: $5,060 |
- | - | - | - | - | - | $2,054 | - |
- - kWh |
- - kW-months/year |
- - lb |
$2,054 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $1,725 Cost: $3,200 |
- | - | - | - | - | - | $1,725 | - |
- - kWh |
- - kW-months/year |
- - lb |
$1,725 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $464 Cost: $345 |
- | - | - | - | - | - | $464 | - |
- - kWh |
- - kW-months/year |
- - lb |
$464 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1321 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT |
Savings: $195 Cost: $590 |
$55 | 1,465 | $140 | 1 | - | - | - | - |
$55 1,465 kWh |
$140 1 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,350 Cost: $7,203 |
$2,554 | 67,995 | $2,796 | 20 | - | - | - | - |
$2,554 67,995 kWh |
$2,796 20 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,666 Cost: $120 |
$2,268 | 60,375 | $1,398 | 10 | - | - | - | - |
$2,268 60,375 kWh |
$1,398 10 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,694 Cost: $183 |
$2,554 | 67,995 | $140 | 12 | - | - | - | - |
$2,554 67,995 kWh |
$140 12 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $9,880 Cost: $15,338 |
$4,988 | 132,767 | $4,892 | 35 | - | - | - | - |
$4,988 132,767 kWh |
$4,892 35 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $3,527 Cost: - |
$1,850 | 49,238 | $1,677 | 12 | - | - | - | - |
$1,850 49,238 kWh |
$1,677 12 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS |
Savings: $898,000 Cost: - |
- | - | - | - | $898,000 | 103,430 | - | - |
- - kWh |
- - kW-months/year |
$898,000 103,430 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $76,000 Cost: - |
- | - | - | - | $76,000 | 3,138 | - | - |
- - kWh |
- - kW-months/year |
$76,000 3,138 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $1,003,555 Cost: $32,039 |
$14,269 | 379,835 | $11,043 | 90 | $974,000 | 106,568 | $4,243 | - | $14,269 379,835 kWh |
$11,043 90 kW-months/year |
$974,000 106,568 lb |
$4,243 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $86,344 Cost: $15,683 |
$4,988 | 132,767 | $4,892 | 35 | $76,000 | 3,138 | $464 | - | $4,988 132,767 kWh |
$4,892 35 kW-months/year |
$76,000 3,138 lb |
$464 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Ancillary Material Cost |