Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri, Rolla |
---|---|
Assessment Year | 1999 |
Principal Product | Bearings and Bushings |
NAICS | n/a |
SIC | 3568 - Power Transmission Equipment, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 92 |
Plant Area (Sq.Ft.) | 41,500 |
Annual Production | 300,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $97,096 | 2,789,273 | kWh | $0.03 |
Electricity Demand | $26,823 | 499 | kW-months/year | $53.75 |
Electricity Fees | $15,448 | - | $ | - |
Natural Gas | $47,037 | 8,065 | MMBtu | $5.83 |
TOTAL ENERGY COSTS | $189,168 | |||
RECOMMENDED SAVINGS* | $88,818 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $22,901 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $4,142 Cost: $5,326 |
$3,336 | 82,649 | $806 | 15 | - | - | - | - |
$3,336 82,649 kWh |
$806 15 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,507 Cost: $5,843 |
$2,023 | 50,117 | $484 | 9 | - | - | - | - |
$2,023 50,117 kWh |
$484 9 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,044 Cost: $40 |
$1,668 | 41,325 | $376 | 7 | - | - | - | - |
$1,668 41,325 kWh |
$376 7 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,393 Cost: $58 |
$1,124 | 27,843 | $269 | 5 | - | - | - | - |
$1,124 27,843 kWh |
$269 5 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,322 Cost: - |
$1,053 | 26,084 | $269 | 5 | - | - | - | - |
$1,053 26,084 kWh |
$269 5 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $63,081 Cost: $12,600 |
- | - | - | - | - | - | $63,081 | - |
- - kWh |
- - kW-months/year |
- - $ |
$63,081 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $14,000 Cost: $3,700 |
- | - | - | - | - | - | $14,000 | - |
- - kWh |
- - kW-months/year |
- - $ |
$14,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $329 Cost: $714 |
- | - | - | - | $329 | - | - | - |
- - kWh |
- - kW-months/year |
$329 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $88,818 Cost: $28,281 |
$9,204 | 228,018 | $2,204 | 41 | $329 | - | $77,081 | - | $9,204 228,018 kWh |
$2,204 41 kW-months/year |
$329 - $ |
$77,081 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $22,901 Cost: $9,124 |
$7,181 | 177,901 | $1,720 | 32 | - | - | $14,000 | - | $7,181 177,901 kWh |
$1,720 32 kW-months/year |
- - $ |
$14,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost |