Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri, Rolla |
---|---|
Assessment Year | 2000 |
Principal Product | Aluminum Die Casting and Stampings |
NAICS | n/a |
SIC | 3363 - Aluminum Die-castings |
Sales | $5,000,000-$10,000,000 |
# of Employees | 61 |
Plant Area (Sq.Ft.) | 65,000 |
Annual Production | 200,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $202,150 | 4,609,906 | kWh | $0.04 |
Electricity Demand | $17,572 | 888 | kW-months/year | $19.79 |
Electricity Fees | $35,335 | - | $ | - |
Natural Gas | $106,843 | 23,483 | MMBtu | $4.55 |
TOTAL ENERGY COSTS | $371,447 | |||
RECOMMENDED SAVINGS* | $22,910 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Liquid (haz) | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Other Liquid (haz) | Solid Waste (non-haz) | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | gal | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,223 Cost: $4,990 |
$2,025 | 39,273 | $198 | 10 | - | - | - | - | - | - |
$2,025 39,273 kWh |
$198 10 kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $2,559 Cost: $4,310 |
$2,282 | 44,256 | $277 | 14 | - | - | - | - | - | - |
$2,282 44,256 kWh |
$277 14 kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,253 Cost: $169 |
$1,194 | 23,154 | $59 | 3 | - | - | - | - | - | - |
$1,194 23,154 kWh |
$59 3 kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,051 Cost: - |
$952 | 18,464 | $99 | 5 | - | - | - | - | - | - |
$952 18,464 kWh |
$99 5 kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $3,000 Cost: - |
- | - | - | - | - | - | $3,000 | 3,000 | - | - |
- - kWh |
- - kW-months/year |
- - gal |
$3,000 3,000 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.6124 BURN WASTE OIL FOR HEAT |
Savings: $5,509 Cost: $3,500 |
- | - | - | - | $5,509 | 2,800 | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,509 2,800 gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.445 INSTALL EQUIPMENT TO MOVE PRODUCT |
Savings: $6,075 Cost: $500 |
- | - | - | - | - | - | - | - | $6,075 | - |
- - kWh |
- - kW-months/year |
- - gal |
- - lb |
$6,075 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $1,240 Cost: $3,700 |
- | - | - | - | - | - | - | - | $1,240 | - |
- - kWh |
- - kW-months/year |
- - gal |
- - lb |
$1,240 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,910 Cost: $17,169 |
$6,453 | 125,147 | $633 | 32 | $5,509 | 2,800 | $3,000 | 3,000 | $7,315 | - | $6,453 125,147 kWh |
$633 32 kW-months/year |
$5,509 2,800 gal |
$3,000 3,000 lb |
$7,315 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | gal | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Liquid (haz) | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Other Liquid (haz) | Solid Waste (non-haz) | Administrative Changes |