Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri, Rolla |
---|---|
Assessment Year | 2000 |
Principal Product | Prepress Operations |
NAICS | n/a |
SIC | 2731 - Book Publishing |
Sales | $50,000,000-$100,000,000 |
# of Employees | 400 |
Plant Area (Sq.Ft.) | 74,000 |
Annual Production | 1,000,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $66,069 | 1,402,110 | kWh | $0.05 |
Electricity Demand | $6,408 | 344 | kW-months/year | $18.63 |
Electricity Fees | $11,559 | - | $ | - |
Natural Gas | $14,305 | 2,494 | MMBtu | $5.74 |
TOTAL ENERGY COSTS | $103,209 | |||
RECOMMENDED SAVINGS* | $34,020 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,302 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,962 Cost: $3,520 |
$1,850 | 33,411 | $112 | 6 | - | - | - | - | - | - |
$1,850 33,411 kWh |
$112 6 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $443 Cost: $495 |
$406 | 7,327 | $37 | 2 | - | - | - | - | - | - |
$406 7,327 kWh |
$37 2 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $21,600 Cost: $52,500 |
$21,600 | 458,382 | - | - | - | - | - | - | - | - |
$21,600 458,382 kWh |
- - kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $1,170 Cost: - |
- | - | - | - | $1,170 | 52,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,170 52,000 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,948 Cost: $750 |
- | - | - | - | - | - | $2,948 | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
$2,948 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.514 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS |
Savings: $5,897 Cost: $12,000 |
- | - | - | - | - | - | - | - | $5,897 | - |
- - kWh |
- - kW-months/year |
- - lb |
- - $ |
$5,897 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $34,020 Cost: $69,265 |
$23,856 | 499,120 | $149 | 8 | $1,170 | 52,000 | $2,948 | - | $5,897 | - | $23,856 499,120 kWh |
$149 8 kW-months/year |
$1,170 52,000 lb |
$2,948 - $ |
$5,897 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,302 Cost: $16,015 |
$2,256 | 40,738 | $149 | 8 | - | - | - | - | $5,897 | - | $2,256 40,738 kWh |
$149 8 kW-months/year |
- - lb |
- - $ |
$5,897 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost |