IAC Assessment: MS0106
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MS0106
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Mississippi State
Assessment Year 1998
Principal Product Frozen and Prepared Fresh Catfish
NAICS n/a
SIC 2092 - Fresh Or Frozen Prepared Fish
Sales $10,000,000-$50,000,000
# of Employees 300
Plant Area (Sq.Ft.) 38,000
Annual Production 33,000,000 Pounds
Production Hrs. Annual 2,080
Location (State) MS
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $290,183 5,963,072 kWh $0.05
Electricity Demand $61,583 15,606 kW-months/year $3.95
Electricity Fees $(-6,678) - $ -
LPG $28,279 4,336 MMBtu $6.52
TOTAL ENERGY COSTS $374,567
RECOMMENDED SAVINGS* $19,118 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $6,089
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Administrative Changes Electricity Usage Electricity Demand Electricity Fees Administrative Changes
$ kWh $ kW-months/year $ $ $ $
01: 2.7132 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS Savings:
$3,778
Cost:
$4,246
$3,889 86,460 - - $(-111) - - - $3,889
86,460
kWh
-
-
kW-months/year
$(-111)
-
$
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,362
Cost:
$13,737
$4,796 106,682 $693 180 $(-127) - - - $4,796
106,682
kWh
$693
180
kW-months/year
$(-127)
-
$
-
-
$
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$7,667
Cost:
$22,209
$7,893 175,557 - - $(-226) - - - $7,893
175,557
kWh
-
-
kW-months/year
$(-226)
-
$
-
-
$
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$723
Cost:
-
$664 14,654 $77 20 $(-18) - - - $664
14,654
kWh
$77
20
kW-months/year
$(-18)
-
$
-
-
$
05: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS Savings:
$1,588
Cost:
$1,920
- - - - - - $1,588 - -
-
kWh
-
-
kW-months/year
-
-
$
$1,588
-
$
TOTAL RECOMMENDED Savings:
$19,118
Cost:
$42,112
$17,242 383,353 $770 200 $(-482) - $1,588 - $17,242
383,353
kWh
$770
200
kW-months/year
$(-482)
-
$
$1,588
-
$
TOTAL IMPLEMENTED Savings:
$6,089
Cost:
$6,166
$4,553 101,114 $77 20 $(-129) - $1,588 - $4,553
101,114
kWh
$77
20
kW-months/year
$(-129)
-
$
$1,588
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Administrative Changes Electricity Usage Electricity Demand Electricity Fees Administrative Changes