Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri-Columbia |
---|---|
Assessment Year | 2010 |
Principal Product | paving and roofing products |
NAICS | 324121 - Asphalt Paving Mixture and Block Manufacturing |
SIC | 2951 - Asphalt Paving Mixtures And Blocks |
Sales | $10,000,000-$50,000,000 |
# of Employees | 10 |
Plant Area (Sq.Ft.) | 65,000 |
Annual Production | 15,000 Tons |
Production Hrs. Annual | 6,240 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $113,965 | 1,640,285 | kWh | $0.07 |
Electricity Demand | $28,365 | 5,028 | kW-months/year | $5.64 |
Natural Gas | $234,667 | 31,356 | MMBtu | $7.48 |
TOTAL ENERGY COSTS | $376,997 | |||
RECOMMENDED SAVINGS* | $97,150 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,366 Cost: $1,054 |
- | - | - | - | $2,366 | 301 |
- - kWh |
- - kW-months/year |
$2,366 301 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $3,852 Cost: $940 |
- | - | - | - | $3,852 | 490 |
- - kWh |
- - kW-months/year |
$3,852 490 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $24,485 Cost: $30,000 |
- | - | - | - | $24,485 | 3,119 |
- - kWh |
- - kW-months/year |
$24,485 3,119 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $60,827 Cost: $30,000 |
- | - | - | - | $60,827 | 7,749 |
- - kWh |
- - kW-months/year |
$60,827 7,749 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $2,942 Cost: $17,975 |
$2,625 | 29,170 | $317 | 57 | - | - |
$2,625 29,170 kWh |
$317 57 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,678 Cost: $2,840 |
$2,390 | 26,557 | $288 | 51 | - | - |
$2,390 26,557 kWh |
$288 51 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $97,150 Cost: $82,809 |
$5,015 | 55,727 | $605 | 108 | $91,530 | 11,659 | $5,015 55,727 kWh |
$605 108 kW-months/year |
$91,530 11,659 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |