Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri-Columbia |
---|---|
Assessment Year | 2019 |
Principal Product | Cups, Lids, and Food Packaging |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $100,000,000-$500,000,000 |
# of Employees | 750 |
Plant Area (Sq.Ft.) | 440,000 |
Annual Production | 120,000,000 Pounds |
Production Hrs. Annual | 8,736 |
Location (State) | KS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $5,660,085 | 141,237,583 | kWh | $0.04 |
Electricity Demand | $4,850,848 | 234,654 | kW-months/year | $20.67 |
Electricity Fees | $(-408,570) | - | $ | - |
Natural Gas | $73,735 | 21,745 | MMBtu | $3.39 |
TOTAL ENERGY COSTS | $10,176,098 | |||
RECOMMENDED SAVINGS* | $1,775,396 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,685,945 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2622 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL |
Savings: $902,475 Cost: $6,762,500 |
$528,968 | 13,191,219 | $373,507 | 18,070 | - | - | - | - |
$528,968 13,191,219 kWh |
$373,507 18,070 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $382,507 Cost: $601,250 |
$224,196 | 5,590,911 | $158,311 | 7,659 | - | - | - | - |
$224,196 5,590,911 kWh |
$158,311 7,659 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $176,232 Cost: $3,250 |
- | - | $176,232 | 8,526 | - | - | - | - |
- - kWh |
$176,232 8,526 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.1192 REDUCE SCRAP PRODUCTION |
Savings: $126,263 Cost: $207,500 |
$43,527 | 1,085,493 | $30,736 | 1,487 | - | - | $52,000 | - |
$43,527 1,085,493 kWh |
$30,736 1,487 kW-months/year |
- - MMBtu |
$52,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $53,880 Cost: $7,750 |
$31,580 | 787,534 | $22,300 | 1,079 | - | - | - | - |
$31,580 787,534 kWh |
$22,300 1,079 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $45,917 Cost: $2,907 |
$45,917 | 1,145,044 | - | - | - | - | - | - |
$45,917 1,145,044 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $42,284 Cost: $13,051 |
$24,784 | 618,111 | $17,500 | 846 | - | - | - | - |
$24,784 618,111 kWh |
$17,500 846 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $35,571 Cost: $11,900 |
- | - | - | - | $35,571 | 10,493 | - | - |
- - kWh |
- - kW-months/year |
$35,571 10,493 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $5,558 Cost: $870 |
$3,258 | 81,225 | $2,300 | 111 | - | - | - | - |
$3,258 81,225 kWh |
$2,300 111 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $4,709 Cost: $200 |
$2,766 | 68,980 | $1,943 | 94 | - | - | - | - |
$2,766 68,980 kWh |
$1,943 94 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $1,775,396 Cost: $7,611,178 |
$904,996 | 22,568,517 | $782,829 | 37,872 | $35,571 | 10,493 | $52,000 | - | $904,996 22,568,517 kWh |
$782,829 37,872 kW-months/year |
$35,571 10,493 MMBtu |
$52,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,685,945 Cost: $7,591,528 |
$873,416 | 21,780,983 | $760,529 | 36,793 | - | - | $52,000 | - | $873,416 21,780,983 kWh |
$760,529 36,793 kW-months/year |
- - MMBtu |
$52,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Primary Raw Material |