Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri-Columbia |
---|---|
Assessment Year | 2020 |
Principal Product | Aircraft Components |
NAICS | 334514 - Totalizing Fluid Meter and Counting Device Manufacturing |
SIC | 3824 - Fluid Meters And Counting Devices |
Sales | $50,000,000-$100,000,000 |
# of Employees | 111 |
Plant Area (Sq.Ft.) | 76,000 |
Annual Production | 20,000 Units |
Production Hrs. Annual | 2,400 |
Location (State) | KS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $118,202 | 2,158,275 | kWh | $0.05 |
Electricity Demand | $110,709 | 6,280 | kW-months/year | $17.63 |
Electricity Fees | $2,031 | - | $ | - |
TOTAL ENERGY COSTS | $230,942 | |||
RECOMMENDED SAVINGS* | $25,307 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $15,689 Cost: $41,089 |
$7,440 | 114,550 | $8,249 | 516 | - | - |
$7,440 114,550 kWh |
$8,249 516 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $6,118 Cost: $3,400 |
- | - | $6,118 | 269 | - | - |
- - kWh |
$6,118 269 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,574 Cost: $1,660 |
$602 | 15,510 | $1,772 | 78 | $(-800) | - |
$602 15,510 kWh |
$1,772 78 kW-months/year |
$(-800) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $1,502 Cost: $3,320 |
$383 | 9,858 | $1,119 | 49 | - | - |
$383 9,858 kWh |
$1,119 49 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $424 Cost: $430 |
$106 | 2,738 | $318 | 14 | - | - |
$106 2,738 kWh |
$318 14 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $25,307 Cost: $49,899 |
$8,531 | 142,656 | $17,576 | 926 | $(-800) | - | $8,531 142,656 kWh |
$17,576 926 kW-months/year |
$(-800) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes |