Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri-Columbia |
---|---|
Assessment Year | 2021 |
Principal Product | CNC machines |
NAICS | 333517 - Machine Tool Manufacturing |
SIC | 3541 - Machine Tools, Metal Cutting Types |
Sales | $1,000,000-$5,000,000 |
# of Employees | 40 |
Plant Area (Sq.Ft.) | 47,000 |
Annual Production | 26 Units |
Production Hrs. Annual | 2,600 |
Location (State) | KS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $69,316 | 795,803 | kWh | $0.09 |
Electricity Demand | $27,144 | 4,508 | kW-months/year | $6.02 |
Electricity Fees | $294 | - | $ | - |
Natural Gas | $7,008 | 1,040 | MMBtu | $6.74 |
TOTAL ENERGY COSTS | $103,762 | |||
RECOMMENDED SAVINGS* | $10,260 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $3,909 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $6,351 Cost: $1,250 |
- | - | $6,351 | 1,055 | - | - |
- - kWh |
$6,351 1,055 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,100 Cost: $6,233 |
$2,350 | 26,975 | $750 | 125 | - | - |
$2,350 26,975 kWh |
$750 125 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $809 Cost: $1,130 |
$765 | 8,786 | $244 | 41 | $(-200) | - |
$765 8,786 kWh |
$244 41 kW-months/year |
$(-200) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $10,260 Cost: $8,613 |
$3,115 | 35,761 | $7,345 | 1,221 | $(-200) | - | $3,115 35,761 kWh |
$7,345 1,221 kW-months/year |
$(-200) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $3,909 Cost: $7,363 |
$3,115 | 35,761 | $994 | 166 | $(-200) | - | $3,115 35,761 kWh |
$994 166 kW-months/year |
$(-200) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes |