IAC Assessment: NC0252
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NC0252
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center North Carolina State
Assessment Year 2003
Principal Product Electrical outlets and switches
NAICS n/a
SIC 3643 - Current-carrying Wiring Devices
Sales $50,000,000-$100,000,000
# of Employees 300
Plant Area (Sq.Ft.) 155,000
Annual Production 100,000,000 Pieces
Production Hrs. Annual 8,400
Location (State) NC
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $364,509 12,647,100 kWh $0.03
Electricity Demand $247,432 26,407 kW-months/year $9.37
Electricity Fees $19,107 - $ -
Natural Gas $27,612 4,031 MMBtu $6.85
TOTAL ENERGY COSTS $658,660
RECOMMENDED SAVINGS* $33,092 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $18,311
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Water Disposal Electricity Usage Electricity Demand Water Disposal
$ kWh $ kW-months/year $ Tgal
01: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$14,411
Cost:
$20,000
$8,714 302,578 $5,697 605 - - $8,714
302,578
kWh
$5,697
605
kW-months/year
-
-
Tgal
02: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT Savings:
$10,800
Cost:
$6,000
$10,800 374,990 - - - - $10,800
374,990
kWh
-
-
kW-months/year
-
-
Tgal
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$240
Cost:
$100
$145 5,040 $95 10 - - $145
5,040
kWh
$95
10
kW-months/year
-
-
Tgal
04: 2.2625 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE Savings:
$1,917
Cost:
$400
$1,306 45,360 $611 65 - - $1,306
45,360
kWh
$611
65
kW-months/year
-
-
Tgal
05: 2.5194 REDESIGN PROCESS Savings:
$4,814
Cost:
$780
$3,281 113,935 $1,533 163 - - $3,281
113,935
kWh
$1,533
163
kW-months/year
-
-
Tgal
06: 2.7228 AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM Savings:
$780
Cost:
$1,000
$384 13,345 $396 38 - - $384
13,345
kWh
$396
38
kW-months/year
-
-
Tgal
07: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) Savings:
$130
Cost:
$350
- - - - $130 - -
-
kWh
-
-
kW-months/year
$130
-
Tgal
TOTAL RECOMMENDED Savings:
$33,092
Cost:
$28,630
$24,630 855,248 $8,332 881 $130 - $24,630
855,248
kWh
$8,332
881
kW-months/year
$130
-
Tgal
TOTAL IMPLEMENTED Savings:
$18,311
Cost:
$8,180
$15,771 547,630 $2,540 266 - - $15,771
547,630
kWh
$2,540
266
kW-months/year
-
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ Tgal
Electricity Usage Electricity Demand Water Disposal Electricity Usage Electricity Demand Water Disposal