Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2003 |
Principal Product | Accessory products for building industry |
NAICS | 332322 - Sheet Metal Work Manufacturing |
SIC | 3444 - Sheet Metalwork |
Sales | $50,000,000-$100,000,000 |
# of Employees | 290 |
Plant Area (Sq.Ft.) | 450,000 |
Annual Production | 17,000,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $228,091 | 4,716,960 | kWh | $0.05 |
Electricity Demand | $55,880 | 11,383 | kW-months/year | $4.91 |
Electricity Fees | $9,138 | - | $ | - |
LPG | $131,505 | 16,290 | MMBtu | $8.07 |
TOTAL ENERGY COSTS | $424,614 | |||
RECOMMENDED SAVINGS* | $51,895 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $693 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | LPG | Water Disposal | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | LPG | Water Disposal | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.446 AUTOMATE FINISHING PROCESS |
Savings: $29,974 Cost: $26,350 |
$(-370) | (-8,400) | $(-256) | (-50) | - | - | - | - | $33,600 | - | $(-3,000) | - |
$(-370) (-8,400) kWh |
$(-256) (-50) kW-months/year |
- - MMBtu |
- - Tgal |
$33,600 - $ |
$(-3,000) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2427 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS |
Savings: $9,563 Cost: $8,000 |
- | - | - | - | $9,563 | 1,185 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$9,563 1,185 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1113 REDUCE COMBUSTION AIR FLOW TO OPTIMUM |
Savings: $10,491 Cost: $2,000 |
- | - | - | - | $10,491 | 1,300 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$10,491 1,300 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $693 Cost: $500 |
$3,485 | 79,200 | $808 | 158 | - | - | - | - | $(-2,400) | - | $(-1,200) | - |
$3,485 79,200 kWh |
$808 158 kW-months/year |
- - MMBtu |
- - Tgal |
$(-2,400) - $ |
$(-1,200) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $162 Cost: $329 |
- | - | - | - | $162 | 20 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$162 20 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4153 USE COUNTER CURRENT RINSING TO REDUCE WASTE WATER |
Savings: $1,012 Cost: $300 |
- | - | - | - | - | - | $1,012 | 120,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,012 120,000 Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $51,895 Cost: $37,479 |
$3,115 | 70,800 | $552 | 108 | $20,216 | 2,505 | $1,012 | 120,000 | $31,200 | - | $(-4,200) | - | $3,115 70,800 kWh |
$552 108 kW-months/year |
$20,216 2,505 MMBtu |
$1,012 120,000 Tgal |
$31,200 - $ |
$(-4,200) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $693 Cost: $500 |
$3,485 | 79,200 | $808 | 158 | - | - | - | - | $(-2,400) | - | $(-1,200) | - | $3,485 79,200 kWh |
$808 158 kW-months/year |
- - MMBtu |
- - Tgal |
$(-2,400) - $ |
$(-1,200) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | LPG | Water Disposal | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | LPG | Water Disposal | Personnel Changes | Administrative Changes |