IAC Assessment: NC0380
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NC0380
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center North Carolina State
Assessment Year 2008
Principal Product Parts for construction equipment
NAICS 333120 - Construction Machinery Manufacturing
SIC 3531 - Construction Machinery
Sales $10,000,000-$50,000,000
# of Employees 200
Plant Area (Sq.Ft.) 98,500
Annual Production 15,000,000 Pounds
Production Hrs. Annual 7,200
Location (State) NC
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $271,835 5,936,625 kWh $0.05
Electricity Demand $106,145 12,662 kW-months/year $8.38
Electricity Fees $129,509 - $ -
TOTAL ENERGY COSTS $507,489
RECOMMENDED SAVINGS* $294,176 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $2,147
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
01: 2.2425 USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER Savings:
$8,150
Cost:
$8,000
- - - - $8,150 1,000 - - - - - - -
-
kWh
-
-
kW-months/year
$8,150
1,000
MMBtu
-
-
$
-
-
$
-
-
$
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$9,853
Cost:
$4,500
- - - - $9,853 1,209 - - - - - - -
-
kWh
-
-
kW-months/year
$9,853
1,209
MMBtu
-
-
$
-
-
$
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$864
Cost:
$100
$1,352 29,520 $412 49 - - $(-600) - - - $(-300) - $1,352
29,520
kWh
$412
49
kW-months/year
-
-
MMBtu
$(-600)
-
$
-
-
$
$(-300)
-
$
04: 4.321 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES Savings:
$168,000
Cost:
$120,000
- - - - - - $88,000 - $80,000 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$88,000
-
$
$80,000
-
$
-
-
$
05: 4.424 IMPROVE SPACE COMFORT CONDITIONING Savings:
$89,762
Cost:
$37,500
- - $(-6,238) (-98,597) - - $96,000 - - - - - -
-
kWh
$(-6,238)
(-98,597)
kW-months/year
-
-
MMBtu
$96,000
-
$
-
-
$
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$16,126
Cost:
$91,580
$17,619 384,768 $5,374 641 - - - - - - $(-6,867) - $17,619
384,768
kWh
$5,374
641
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
$(-6,867)
-
$
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$138
Cost:
$980
$106 2,307 $32 4 - - - - - - - - $106
2,307
kWh
$32
4
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
08: 2.4151 DEVELOP A REPAIR/REPLACE POLICY Savings:
$1,283
Cost:
$1,540
$983 21,476 $300 36 - - - - - - - - $983
21,476
kWh
$300
36
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$294,176
Cost:
$264,200
$20,060 438,071 $(-120) (-97,867) $18,003 2,209 $183,400 - $80,000 - $(-7,167) - $20,060
438,071
kWh
$(-120)
(-97,867)
kW-months/year
$18,003
2,209
MMBtu
$183,400
-
$
$80,000
-
$
$(-7,167)
-
$
TOTAL IMPLEMENTED Savings:
$2,147
Cost:
$1,640
$2,335 50,996 $712 85 - - $(-600) - - - $(-300) - $2,335
50,996
kWh
$712
85
kW-months/year
-
-
MMBtu
$(-600)
-
$
-
-
$
$(-300)
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost